Energy Projects Near You

Solar, wind and battery projects near Fordingbridge (SP6)

7 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of SP6 (New Forest): 4 approved but not yet running, 2 operational. The largest live scheme is Hamer Warren Solar Farm (23 MW solar farm, under construction since 1 January 2023), 5.2 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

7projects within 10 km
0awaiting a decision
4approved, not running
2operational

Projects within 10 km of SP6

Projects of 1 MW and more (5)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Cross Roads Plantationsolar farmsolar farm5operationalupdated Aug 2017Aug 2014granted Nov 2014Aug 2017Dorset4.2
Warren Park Solar Farmsolar farmsolar farm5permission expiredupdated Jul 2020Sep 2015granted Dec 2015Jul 2020Dorset4.7
Hamer Warren Solar Farmsolar farmsolar farm23under constructionupdated Jan 2024Oct 2020granted Feb 2021Jan 2024New Forest5.2
Land Adj Harmer Warren Quarrybattery storagebattery storage10under constructionupdated Dec 2022Nov 2017—Dec 2022New Forest5.6
Verwood Solar Farmsolar farmsolar farm20.4operationalupdated May 2015Apr 2014granted Jul 2014May 2015Dorset9.7
Smaller schemes under 1 MW, mostly rooftop solar (2)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Station Mill, Ashford Roadrooftop solarrooftop solar0.2approved, not builtupdated Mar 2023Feb 2023granted Mar 2023Mar 2023New Forest1.0
Batten Road, Downtonrooftop solarrooftop solar0.5approved, not builtupdated Jul 2022Jun 2022granted Aug 2022Jul 2022Wiltshire7.2

Distance from the average position of the SP6 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm4012023
Rooftop solar202000.7
Battery storage1010010

MW in pipeline: pending, approved and under-construction capacity.

How New Forest decides solar, wind and battery applications

ApplicationsNew ForestUK
Decided applications (solar, wind, battery)2610,236
Refused7 (27%)19%
Solar refused6 of 2212%
Battery storage refused1 of 416%
Median time from submission to decision11.0 weeks17.0 weeks
Appeals lodged / allowed2 / 0—

All projects in New Forest

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.