Hamer Warren Solar Farm (23 MW)

Hamer Warren Solar Farm is a 23 MW solar farm project in New Forest, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: under construction since 1 January 2023; the record was last updated on 30 January 2024.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

23 MWsolar farm
under constructionstatus in REPD
30 January 2024record last updated
New Forestcouncil area

Planning timeline

DateStage
1 October 2020Application submitted
3 February 2021Planning permission granted
1 January 2023Construction started

Project details

Technology
solar farm
Capacity
23 MW
Status (REPD)
under construction
Record last updated
30 January 2024
Operator or applicant
Somerley Estate
Planning authority
New Forest
Planning application reference
20/11073
Site area
38.8 ha
Address (REPD)
Hamer Warren, Somerley, Ringwood
Council area (by location)
New Forest
Time to decision
18 weeks
REPD reference
8094

Who decides

ApplicationsNew ForestUK
Decided applications (solar, wind, battery)2610,236
Refused7 (27%)19%
Solar refused6 of 2212%
Battery storage refused1 of 416%
Median time from submission to decision11.0 weeks17.0 weeks
Appeals lodged / allowed2 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Land Adj Harmer Warren Quarrybattery storage10under construction0.4
Warren Park Solar Farmsolar farm5permission expired2.1
Cross Roads Plantationsolar farm5operational2.8
Verwood Solar Farmsolar farm20.4operational5.7
Homeland Solar Farmsolar farm13.2operational6.1
Holt Roadbattery storage47.5approved, not built7.0
Wedgehill Farmsolar farm13operational7.0
Mannington Battery Energy Storage Systembattery storage49.9under construction7.9
Woodlands Manor Farm, Horton Solar Farmsolar farm30approved, not built8.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.8902, -1.8115).