Mannington Battery Energy Storage System (49.9 MW)

Mannington Battery Energy Storage System is a 49.9 MW battery storage project in Dorset, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: under construction since 1 April 2025; the record was last updated on 26 March 2021.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWbattery storage
under constructionstatus in REPD
26 March 2021record last updated
Dorsetcouncil area

Planning timeline

DateStage
22 January 2021Application submitted
2 July 2021Planning permission granted
1 April 2025Construction started

Project details

Technology
battery storage (stand-alone storage)
Capacity
49.9 MW
Status (REPD)
under construction
Record last updated
26 March 2021
Operator or applicant
EDF Energy Renewables
Planning authority
Dorset
Planning application reference
3/21/0137/FUL
Address (REPD)
Land off Holt Road
Council area (by location)
Dorset
Time to decision
23 weeks
REPD reference
8833

Who decides

ApplicationsDorsetUK
Decided applications (solar, wind, battery)12510,236
Refused23 (18%)19%
Solar refused15 of 10512%
Onshore wind refused5 of 545%
Battery storage refused3 of 1516%
Median time from submission to decision19.0 weeks17.0 weeks
Appeals lodged / allowed6 / 6—

Other large projects within 10 km

ProjectTypeMWStatuskm
Holt Roadbattery storage47.5approved, not built0.9
Wedgehill Farmsolar farm13operational1.4
Verwood Solar Farmsolar farm20.4operational2.3
Homeland Solar Farmsolar farm13.2operational2.6
Woodlands Manor Farm, Horton Solar Farmsolar farm30approved, not built3.7
Bedborough Farmsolar farm7operational3.8
North Farm, Horton Solar Farmsolar farm19approved, not built5.1
Chapel Lane Parley Solar Farm Phase 2solar farm36operational6.7
Chapel Lane Parley Solar Farm Phase 1solar farm20operational6.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.8484, -1.9018).