Energy Projects Near You

Homeland Solar Farm (13.2 MW)

Homeland Solar Farm is a 13.2 MW solar farm project in Dorset, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 March 2014; the record was last updated on 7 January 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

13.2 MWsolar farm
operationalstatus in REPD
7 January 2015record last updated
Dorsetcouncil area

Planning timeline

DateStage
28 May 2013Application submitted
8 October 2013Planning permission granted
1 December 2013Construction started
1 March 2014Operational

Project details

Technology
solar farm
Capacity
13.2 MW
Status (REPD)
operational
Record last updated
7 January 2015
Operator or applicant
Foresight
Planning authority
Dorset
Planning application reference
3/13/0470/FUL
Address (REPD)
Homeland Farm, Ringwood Road, Three Legged Cross, Wimborne, Dorset
Council area (by location)
Dorset
Time to decision
19 weeks
REPD reference
1761

Who decides

ApplicationsDorsetUK
Decided applications (solar, wind, battery)12510,236
Refused23 (18%)19%
Solar refused15 of 10512%
Onshore wind refused5 of 545%
Battery storage refused3 of 1516%
Median time from submission to decision19.0 weeks17.0 weeks
Appeals lodged / allowed6 / 6—

Other large projects within 10 km

ProjectTypeMWStatuskm
Holt Roadbattery storage47.5approved, not built1.8
Verwood Solar Farmsolar farm20.4operational2.4
Mannington Battery Energy Storage Systembattery storage49.9under construction2.6
Wedgehill Farmsolar farm13operational3.0
Bedborough Farmsolar farm7operational5.3
Chapel Lane Parley Solar Farm Phase 2solar farm36operational5.7
Land Adj Harmer Warren Quarrybattery storage10under construction5.7
Woodlands Manor Farm, Horton Solar Farmsolar farm30approved, not built5.8
Parley Renewable Energy Park (PV)solar farm5refused6.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.847, -1.8648).