Energy Projects Near You

Chapel Lane Parley Solar Farm Phase 2 (36 MW)

Chapel Lane Parley Solar Farm Phase 2 is a 36 MW solar farm project in Bournemouth, Christchurch and Poole, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 29 August 2014; the record was last updated on 5 November 2014.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

36 MWsolar farm
operationalstatus in REPD
5 November 2014record last updated
Bournemouth, Christchurch and Poolecouncil area

Planning timeline

DateStage
16 July 2013Application submitted
26 September 2013Planning permission granted
1 March 2014Construction started
29 August 2014Operational

Project details

Technology
solar farm
Capacity
36 MW
Status (REPD)
operational
Record last updated
5 November 2014
Operator or applicant
Eco Sustainable Solutions
Planning authority
Bournemouth, Christchurch and Poole
Planning application reference
8/13/0332
Site area
76.7 ha
Address (REPD)
Chapel Lane, Parley, Christchurch, Dorset
Council area (by location)
Bournemouth, Christchurch and Poole
Time to decision
10 weeks
REPD reference
2105

Who decides

ApplicationsBournemouth, Christchurch and PooleUK
Decided applications (solar, wind, battery)3010,236
Refused6 (20%)19%
Solar refused6 of 2812%
Battery storage refused0 of 216%
Median time from submission to decision10.6 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Parley Renewable Energy Park (PV)solar farm5refused0.3
Chapel Lane Parley Solar Farm Phase 1solar farm20operational0.6
Hale Farmsolar farm8operational2.0
Parley Court Solar Farmsolar farm35approved, not built3.0
Bedborough Farmsolar farm7operational5.3
Homeland Solar Farmsolar farm13.2operational5.7
Holt Roadbattery storage47.5approved, not built6.6
Mannington Battery Energy Storage Systembattery storage49.9under construction6.7
Dorset Green Solar Farmsolar farm5operational7.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.7959, -1.8563).