Parley Court Solar Farm (35 MW)

Parley Court Solar Farm is a 35 MW solar farm project in Bournemouth, Christchurch and Poole, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 18 June 2024, not yet built; the record was last updated on 20 February 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

35 MWsolar farm
approved, not builtstatus in REPD
20 February 2026record last updated
Bournemouth, Christchurch and Poolecouncil area

Planning timeline

DateStage
19 November 2021Application submitted
18 June 2024Planning permission granted
18 June 2027Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
35 MW
Status (REPD)
approved, not built
Record last updated
20 February 2026
Operator or applicant
Enviromena Asset Management UK Limited
Planning authority
Bournemouth, Christchurch and Poole
Planning application reference
8/21/1067/FUL
Site area
67.2 ha
Address (REPD)
Parley Green Parley Green Lane Bournemouth
Council area (by location)
Bournemouth, Christchurch and Poole
Time to decision
135 weeks
Contracts for Difference
AR7a
Name in REPD
Parley Court - Solar Farm
REPD reference
10041

Who decides

ApplicationsBournemouth, Christchurch and PooleUK
Decided applications (solar, wind, battery)3010,236
Refused6 (20%)19%
Solar refused6 of 2812%
Battery storage refused0 of 216%
Median time from submission to decision10.6 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Hale Farmsolar farm8operational1.0
Chapel Lane Parley Solar Farm Phase 1solar farm20operational2.5
Parley Renewable Energy Park (PV)solar farm5refused2.7
Chapel Lane Parley Solar Farm Phase 2solar farm36operational3.0
Dorset Green Solar Farmsolar farm5operational6.2
Bedborough Farmsolar farm7operational6.8
Waterditch Farm Solar Farm & Battery Storagesolar farm49.9application submitted7.8
Waterditch Solar Farmsolar farm18operational7.9
Christchurch Energysolar farm18operational8.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.7694, -1.8634).