Bedborough Farm (7 MW solar farm)

Bedborough Farm is a 7 MW solar farm project in Dorset, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 26 February 2016; the record was last updated on 4 March 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

7 MWsolar farm
operationalstatus in REPD
4 March 2016record last updated
Dorsetcouncil area

Planning timeline

DateStage
14 August 2014Application submitted
3 November 2014Planning permission granted
15 July 2015Construction started
26 February 2016Operational

Project details

Technology
solar farm
Capacity
7 MW
Status (REPD)
operational
Record last updated
4 March 2016
Operator or applicant
Solstice Renewables Ltd
Planning authority
Dorset
Planning application reference
3/14/0790/FUL
Site area
12.5 ha
Address (REPD)
Bedborough Farm, Land At Uddens Drive Wimborne Dorset
Council area (by location)
Dorset
Time to decision
12 weeks
REPD reference
2114

Who decides

ApplicationsDorsetUK
Decided applications (solar, wind, battery)12510,236
Refused23 (18%)19%
Solar refused15 of 10512%
Onshore wind refused5 of 545%
Battery storage refused3 of 1516%
Median time from submission to decision19.0 weeks17.0 weeks
Appeals lodged / allowed6 / 6—

Other large projects within 10 km

ProjectTypeMWStatuskm
Mannington Battery Energy Storage Systembattery storage49.9under construction3.8
Holt Roadbattery storage47.5approved, not built4.4
Wedgehill Farmsolar farm13operational5.2
Chapel Lane Parley Solar Farm Phase 1solar farm20operational5.3
Homeland Solar Farmsolar farm13.2operational5.3
Chapel Lane Parley Solar Farm Phase 2solar farm36operational5.3
Parley Renewable Energy Park (PV)solar farm5refused5.5
Dorset Green Solar Farmsolar farm5operational5.6
Hale Farmsolar farm8operational6.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.8173, -1.9243).