Solar, wind and battery projects near Wimborne (BH21)
38 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of BH21 (Dorset): 2 are waiting for a planning decision, 18 approved but not yet running, 14 operational. The largest live scheme is Mannington Battery Energy Storage System (49.9 MW battery storage, under construction since 1 April 2025), 6.5 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of BH21
Projects of 1 MW and more (22)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Bedborough Farmsolar farm | solar farm | 7 | operationalupdated Mar 2016 | Aug 2014 | granted Nov 2014 | Mar 2016 | Dorset | 3.6 |
| Dorset Green Solar Farmsolar farm | solar farm | 5 | operationalupdated May 2022 | Mar 2021 | granted Jul 2021 | May 2022 | Bournemouth, Christchurch and Poole | 5.0 |
| Whites Pit, Arena Waysolar farm | solar farm | 2 | approved, not builtupdated Jan 2024 | Sep 2023 | granted Dec 2023 | Jan 2024 | Bournemouth, Christchurch and Poole | 5.1 |
| Mannington Battery Energy Storage Systembattery storage | battery storage | 49.9 | under constructionupdated Mar 2021 | Jan 2021 | granted Jul 2021 | Mar 2021 | Dorset | 6.5 |
| Henbury Quarrysolar farm | solar farm | 3.9 | operationalupdated May 2015 | Sep 2013 | granted May 2014 | May 2015 | Dorset | 6.7 |
| Holt Roadbattery storage | battery storage | 47.5 | approved, not builtupdated Sep 2024 | Nov 2023 | granted Jul 2024 | Sep 2024 | Dorset | 7.3 |
| Woodlands Manor Farm, Horton Solar Farmsolar farm | solar farm | 30 | approved, not builtupdated Jun 2025 | Jun 2023 | granted May 2025 | Jun 2025 | Dorset | 7.4 |
| Wedgehill Farmsolar farm | solar farm | 13 | operationalupdated Mar 2015 | Jul 2013 | granted Jan 2014 | Mar 2015 | Dorset | 7.5 |
| North Farm, Horton Solar Farmsolar farm | solar farm | 19 | approved, not builtupdated Jun 2025 | May 2023 | granted May 2025 | Jun 2025 | Dorset | 7.6 |
| Chapel Lane Parley Solar Farm Phase 3solar farm | solar farm | 4 | operationalupdated Nov 2015 | Aug 2014 | granted Jan 2015 | Nov 2015 | Dorset | 7.8 |
| Woodtown Farmsolar farm | solar farm | 3.8 | operationalupdated Mar 2016 | Oct 2014 | granted Oct 2015 | Mar 2016 | Dorset | 8.3 |
| Chapel Lane Parley Solar Farm Phase 1solar farm | solar farm | 20 | operationalupdated Sep 2014 | Nov 2012 | granted Mar 2013 | Sep 2014 | Bournemouth, Christchurch and Poole | 8.3 |
| Chapel Lane Parley Solar Farm Phase 2solar farm | solar farm | 36 | operationalupdated Nov 2014 | Jul 2013 | granted Sep 2013 | Nov 2014 | Bournemouth, Christchurch and Poole | 8.5 |
| Parley Renewable Energy Park (PV)solar farm | solar farm | 5 | refusedupdated Sep 2012 | Dec 2010 | refused Mar 2011 | Sep 2012 | Bournemouth, Christchurch and Poole | 8.6 |
| Hale Farmsolar farm | solar farm | 8 | operationalupdated Mar 2016 | Oct 2014 | granted Sep 2015 | Mar 2016 | Dorset | 8.6 |
| Homeland Solar Farmsolar farm | solar farm | 13.2 | operationalupdated Jan 2015 | May 2013 | granted Oct 2013 | Jan 2015 | Dorset | 8.6 |
| Verwood Solar Farmsolar farm | solar farm | 20.4 | operationalupdated May 2015 | Apr 2014 | granted Jul 2014 | May 2015 | Dorset | 8.7 |
| Curtiss Wright Controls, Enterprise Wayrooftop solar | rooftop solar | 1 | approved, not builtupdated Nov 2024 | Aug 2024 | granted Nov 2024 | Nov 2024 | Bournemouth, Christchurch and Poole | 9.1 |
| Parley Court Solar Farmsolar farm | solar farm | 35 | approved, not builtupdated Feb 2026 | Nov 2021 | granted Jun 2024 | Feb 2026 | Bournemouth, Christchurch and Poole | 9.1 |
| Post Farm, Lytchett Minsterbattery storage | battery storage | 32 | approved, not builtupdated Jan 2025 | May 2023 | granted Nov 2024 | Jan 2025 | Dorset | 9.2 |
| Race farmsolar farm | solar farm | 6.1 | operationalupdated Jan 2017 | Mar 2013 | granted Jun 2013 | Jan 2017 | Dorset | 9.4 |
| Holes Baybattery storage | battery storage | 15 | operationalupdated Mar 2026 | Feb 2017 | granted Sep 2017 | Mar 2026 | Bournemouth, Christchurch and Poole | 9.6 |
Smaller schemes under 1 MW, mostly rooftop solar (16)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Canford School, Sports Centrerooftop solar | rooftop solar | 0.2 | approved, not builtupdated May 2024 | Mar 2024 | granted May 2024 | May 2024 | Bournemouth, Christchurch and Poole | 3.0 |
| Whittle Boxland, Whittle Road Energy Storage Facilitybattery storage | battery storage | 0.2 | approved, not built may be out of dateupdated Nov 2022 | Sep 2022 | granted Nov 2022 | Nov 2022 | Dorset | 4.0 |
| Dorset Green Batterybattery storage | battery storage | — | operationalupdated Jul 2022 | Mar 2021 | granted Jul 2021 | Jul 2022 | Bournemouth, Christchurch and Poole | 5.0 |
| Ferndown Upper Schoolrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Jan 2022 | Nov 2021 | granted Jan 2022 | Jan 2022 | Dorset | 5.0 |
| Cherry Groverooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jan 2022 | Nov 2021 | granted Jan 2022 | Jan 2022 | Dorset | 5.3 |
| Sainsburys Supermarket, Ringwood Roadrooftop solar | rooftop solar | 0.4 | approved, not builtupdated Apr 2025 | Feb 2025 | granted Mar 2025 | Apr 2025 | Dorset | 7.0 |
| Wessex Water Palmersford Sewage Treatment, Humber Roadsolar farm | solar farm | — | application withdrawnupdated Jan 2023 | Nov 2022 | — | Jan 2023 | Dorset | 7.6 |
| David Lloyd Leisurerooftop solar | rooftop solar | 0.6 | approved, not builtupdated Oct 2023 | Aug 2023 | granted Oct 2023 | Oct 2023 | Bournemouth, Christchurch and Poole | 7.7 |
| David Lloyd Leisurerooftop solar | rooftop solar | 0.5 | refusedupdated Aug 2023 | Jun 2023 | refused Jul 2023 | Aug 2023 | Bournemouth, Christchurch and Poole | 7.7 |
| Big Yellow Self Storage, Nuffield Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Oct 2022 | Aug 2022 | granted Oct 2022 | Oct 2022 | Bournemouth, Christchurch and Poole | 8.0 |
| The Alpha Centre, Upton Roadrooftop solar | rooftop solar | 0.4 | approved, not builtupdated Feb 2023 | Dec 2022 | granted Feb 2023 | Feb 2023 | Bournemouth, Christchurch and Poole | 8.5 |
| Fleetspoint Business Centre, Willis Wayrooftop solar | rooftop solar | 0.3 | application submittedupdated Oct 2024 | Oct 2024 | — | Oct 2024 | Bournemouth, Christchurch and Poole | 9.1 |
| Fleetspoint Business Centre, Willis Wayrooftop solar | rooftop solar | 0.2 | application submittedupdated Oct 2024 | Oct 2024 | — | Oct 2024 | Bournemouth, Christchurch and Poole | 9.1 |
| Sainsburys, Alder Parkrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Jun 2025 | Nov 2024 | granted May 2025 | Jun 2025 | Bournemouth, Christchurch and Poole | 9.3 |
| Wimborne Roadrooftop solar | rooftop solar | 0.1 | approved, not builtupdated Jul 2025 | Apr 2025 | granted Jun 2025 | Jul 2025 | Bournemouth, Christchurch and Poole | 9.5 |
| Lytchett Minster School, Post Green Roadrooftop solar | rooftop solar | 0.3 | application withdrawnupdated May 2026 | Apr 2026 | — | May 2026 | Dorset | 9.9 |
Distance from the average position of the BH21 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 18 | 0 | 4 | 12 | 1 | 86 |
| Rooftop solar | 14 | 2 | 10 | 0 | 1 | 4.2 |
| Battery storage | 6 | 0 | 4 | 2 | 0 | 130 |
MW in pipeline: pending, approved and under-construction capacity.
How Dorset decides solar, wind and battery applications
| Applications | Dorset | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 125 | 10,236 |
| Refused | 23 (18%) | 19% |
| Solar refused | 15 of 105 | 12% |
| Onshore wind refused | 5 of 5 | 45% |
| Battery storage refused | 3 of 15 | 16% |
| Median time from submission to decision | 19.0 weeks | 17.0 weeks |
| Appeals lodged / allowed | 6 / 6 | — |
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near BH21, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.