Post Farm, Lytchett Minster (32 MW battery storage)

Post Farm, Lytchett Minster is a 32 MW battery storage project in Dorset, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 28 November 2024, not yet built; the record was last updated on 13 January 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

32 MWbattery storage
approved, not builtstatus in REPD
13 January 2025record last updated
Dorsetcouncil area

Planning timeline

DateStage
16 May 2023Application submitted
28 November 2024Planning permission granted
28 November 2027Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
32 MW
Status (REPD)
approved, not built
Record last updated
13 January 2025
Operator or applicant
S4N Lytchett Limited
Planning authority
Dorset
Planning application reference
P/FUL/2023/02819
Address (REPD)
Post Farm Lytchett Minster Poole
Council area (by location)
Dorset
Time to decision
80 weeks
Name in REPD
Post Farm, Lytchett Minster - Battery Energy Storage
REPD reference
10291

Who decides

ApplicationsDorsetUK
Decided applications (solar, wind, battery)12510,236
Refused23 (18%)19%
Solar refused15 of 10512%
Onshore wind refused5 of 545%
Battery storage refused3 of 1516%
Median time from submission to decision19.0 weeks17.0 weeks
Appeals lodged / allowed6 / 6—

Other large projects within 10 km

ProjectTypeMWStatuskm
Race farmsolar farm6.1operational1.3
South Newton Farmsolar farm11.3operational3.7
Dolmans Hill (Redbridge Farm) Solar Arrayssolar farm5operational4.2
Holes Baybattery storage15operational4.3
Dorset Green Solar Farmsolar farm5operational7.3
Oaklands Plantationsolar farm5operational8.0
Bottom Plainsolar farm10operational9.1
Mapperton Farmsolar farm24application withdrawn9.1
Trigon Solar Farmsolar farm7operational9.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.7421, -2.0455).