Energy Projects Near You

Trigon Solar Farm (7 MW)

Trigon Solar Farm is a 7 MW solar farm project in Dorset, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 8 March 2013; the record was last updated on 11 April 2013.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

7 MWsolar farm
operationalstatus in REPD
11 April 2013record last updated
Dorsetcouncil area

Planning timeline

DateStage
5 July 2012Application submitted
28 November 2012Planning permission granted
8 March 2013Operational

Project details

Technology
solar farm
Capacity
7 MW
Status (REPD)
operational
Record last updated
11 April 2013
Operator or applicant
Trigon Solar Farm Ltd
Planning authority
Dorset
Planning application reference
6/2012/0415
Site area
18.1 ha
Address (REPD)
Trigon (Trigon House), Wareham
Council area (by location)
Dorset
Time to decision
21 weeks
REPD reference
1060

Who decides

ApplicationsDorsetUK
Decided applications (solar, wind, battery)12510,236
Refused23 (18%)19%
Solar refused15 of 10512%
Onshore wind refused5 of 545%
Battery storage refused3 of 1516%
Median time from submission to decision19.0 weeks17.0 weeks
Appeals lodged / allowed6 / 6—

Other large projects within 10 km

ProjectTypeMWStatuskm
Bottom Plainsolar farm10operational0.6
Oaklands Plantationsolar farm5operational2.2
Stokeford Farmsolar farm28.5operational2.7
Alaska Wind Farmwind farm9.2operational2.8
Woolbridge Solar Parksolar farm5operational4.3
South Newton Farmsolar farm11.3operational6.0
Dolmans Hill (Redbridge Farm) Solar Arrayssolar farm5operational6.7
Part Bushes Farmwind farm24.8refused7.7
Race farmsolar farm6.1operational8.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.7108, -2.1739).