Energy Projects Near You

Part Bushes Farm (24.8 MW wind farm)

Part Bushes Farm is a 24.8 MW wind farm project in Dorset, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 26 October 2004; the record was last updated on 29 June 2011.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

24.8 MWwind farm
refusedstatus in REPD
29 June 2011record last updated
Dorsetcouncil area

Planning timeline

DateStage
1 August 2003Application submitted
26 October 2004Refused by the planning authority

Project details

Technology
wind farm
Capacity
24.8 MW
Status (REPD)
refused
Record last updated
29 June 2011
Operator or applicant
Lower Winterbourne Wind Farm Ltd
Planning authority
Dorset
Planning application reference
2-2003-0765
Address (REPD)
Part Bushes Farm, Riverside Farm and Tomson Farm Anderson and Winterbourne Zelston
Council area (by location)
Dorset
Time to decision
65 weeks
REPD reference
3175

Who decides

ApplicationsDorsetUK
Decided applications (solar, wind, battery)12510,236
Refused23 (18%)19%
Solar refused15 of 10512%
Onshore wind refused5 of 545%
Battery storage refused3 of 1516%
Median time from submission to decision19.0 weeks17.0 weeks
Appeals lodged / allowed6 / 6—

Other large projects within 10 km

ProjectTypeMWStatuskm
Mapperton Farmsolar farm24application withdrawn2.8
Blandford Hill Wind Farmwind farm12refused3.2
Blandford Hill - EV Charging Station & Solar Farmsolar farm15approved, not built4.1
North Farm (Spetisbury)solar farm11.6operational4.3
South Farm Solar Parksolar farm40operational4.7
Dolmans Hill (Redbridge Farm) Solar Arrayssolar farm5operational6.5
The Down Housesolar farm5abandoned6.8
Canada Farmsolar farm8.3operational7.2
Littletonsolar farm12.1operational7.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.78, -2.1824).