Blandford Hill - EV Charging Station & Solar Farm (15 MW)

Blandford Hill - EV Charging Station & Solar Farm is a 15 MW solar farm project in Dorset, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 26 January 2022, not yet built; the record was last updated on 7 April 2021.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

15 MWsolar farm
approved, not builtstatus in REPD
7 April 2021record last updated
Dorsetcouncil area

Planning timeline

DateStage
27 July 2021Application submitted
26 January 2022Planning permission granted

Project details

Technology
solar farm
Capacity
15 MW
Status (REPD)
approved, not built
Record last updated
7 April 2021
Operator or applicant
Naturalis Energy Developments Limited
Planning authority
Dorset
Planning application reference
P/FUL/2021/02622
Site area
37.7 ha
Address (REPD)
Blandford Hill Winterborne Whitechurch
Council area (by location)
Dorset
Time to decision
26 weeks
REPD reference
8461

The scheme also includes 3 MW of battery storage, recorded separately in REPD (approved, not built).

Who decides

ApplicationsDorsetUK
Decided applications (solar, wind, battery)12510,236
Refused23 (18%)19%
Solar refused15 of 10512%
Onshore wind refused5 of 545%
Battery storage refused3 of 1516%
Median time from submission to decision19.0 weeks17.0 weeks
Appeals lodged / allowed6 / 6—

Other large projects within 10 km

ProjectTypeMWStatuskm
Blandford Hill Wind Farmwind farm12refused1.1
Canada Farmsolar farm8.3operational4.0
Part Bushes Farmwind farm24.8refused4.1
North Farm (Spetisbury)solar farm11.6operational4.5
The Down Housesolar farm5abandoned5.0
Mapperton Farmsolar farm24application withdrawn5.8
South Farm Solar Parksolar farm40operational6.2
Littletonsolar farm12.1operational6.4
West Dorset Wind Farmwind farm12.5application withdrawn6.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.8021, -2.2283).