Energy Projects Near You

Littleton (12.1 MW solar farm)

Littleton is a 12.1 MW solar farm project in Dorset, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 23 March 2015; the record was last updated on 14 May 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

12.1 MWsolar farm
operationalstatus in REPD
14 May 2015record last updated
Dorsetcouncil area

Planning timeline

DateStage
23 September 2014Application submitted
9 December 2014Planning permission granted
30 December 2014Construction started
23 March 2015Operational

Project details

Technology
solar farm
Capacity
12.1 MW
Status (REPD)
operational
Record last updated
14 May 2015
Operator or applicant
Lightsource Renewable Energy
Planning authority
Dorset
Planning application reference
2/2014/1066/FUL
Site area
22.3 ha
Address (REPD)
Blandford Forum Bypass, Blandford, St Mary, Dorset
Council area (by location)
Dorset
Time to decision
11 weeks
REPD reference
4840

Who decides

ApplicationsDorsetUK
Decided applications (solar, wind, battery)12510,236
Refused23 (18%)19%
Solar refused15 of 10512%
Onshore wind refused5 of 545%
Battery storage refused3 of 1516%
Median time from submission to decision19.0 weeks17.0 weeks
Appeals lodged / allowed6 / 6—

Other large projects within 10 km

ProjectTypeMWStatuskm
The Down Housesolar farm5abandoned1.7
North Farm (Spetisbury)solar farm11.6operational3.0
South Farm Solar Parksolar farm40operational4.0
Canada Farmsolar farm8.3operational4.4
Blandford Hill Wind Farmwind farm12refused5.8
Mapperton Farmsolar farm24application withdrawn6.0
Blandford Hill - EV Charging Station & Solar Farmsolar farm15approved, not built6.4
Part Bushes Farmwind farm24.8refused7.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.8449, -2.1671).