Energy Projects Near You

South Farm Solar Park (40 MW)

South Farm Solar Park is a 40 MW solar farm project in Dorset, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 16 December 2022; the record was last updated on 21 December 2022.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

40 MWsolar farm
operationalstatus in REPD
21 December 2022record last updated
Dorsetcouncil area

Planning timeline

DateStage
21 June 2019Application submitted
25 June 2020Planning permission granted
6 January 2021Construction started
16 December 2022Operational

Project details

Technology
solar farm
Capacity
40 MW
Status (REPD)
operational
Record last updated
21 December 2022
Operator or applicant
Voltalia UK
Planning authority
Dorset
Planning application reference
2/2019/0850/PAEIA
Site area
71.5 ha
Address (REPD)
South Farm, Field Dairy To Louse Lane, Spetisbury, Blandford Forum
Council area (by location)
Dorset
Time to decision
53 weeks
REPD reference
9360

The scheme also includes 10 MW of battery storage, recorded separately in REPD (operational).

Who decides

ApplicationsDorsetUK
Decided applications (solar, wind, battery)12510,236
Refused23 (18%)19%
Solar refused15 of 10512%
Onshore wind refused5 of 545%
Battery storage refused3 of 1516%
Median time from submission to decision19.0 weeks17.0 weeks
Appeals lodged / allowed6 / 6—

Other large projects within 10 km

ProjectTypeMWStatuskm
North Farm (Spetisbury)solar farm11.6operational2.1
Mapperton Farmsolar farm24application withdrawn2.4
Littletonsolar farm12.1operational4.0
The Down Housesolar farm5abandoned4.6
Part Bushes Farmwind farm24.8refused4.7
Blandford Hill Wind Farmwind farm12refused5.2
Blandford Hill - EV Charging Station & Solar Farmsolar farm15approved, not built6.2
Canada Farmsolar farm8.3operational6.7
Dolmans Hill (Redbridge Farm) Solar Arrayssolar farm5operational7.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.8132, -2.1415).