Woolbridge Solar Park (5 MW)

Woolbridge Solar Park is a 5 MW solar farm project in Dorset, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 18 June 2014; the record was last updated on 23 August 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
23 August 2017record last updated
Dorsetcouncil area

Planning timeline

DateStage
5 August 2013Application submitted
10 December 2013Planning permission granted
15 April 2014Construction started
18 June 2014Operational

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
23 August 2017
Operator or applicant
Good Energy Generation
Planning authority
Dorset
Planning application reference
6/2013/0446
Site area
10.5 ha
Address (REPD)
Tout Hill, Woolbridge
Council area (by location)
Dorset
Time to decision
18 weeks
REPD reference
1902

Who decides

ApplicationsDorsetUK
Decided applications (solar, wind, battery)12510,236
Refused23 (18%)19%
Solar refused15 of 10512%
Onshore wind refused5 of 545%
Battery storage refused3 of 1516%
Median time from submission to decision19.0 weeks17.0 weeks
Appeals lodged / allowed6 / 6—

Other large projects within 10 km

ProjectTypeMWStatuskm
Stokeford Farmsolar farm28.5operational3.2
Alaska Wind Farmwind farm9.2operational3.2
Trigon Solar Farmsolar farm7operational4.3
Bottom Plainsolar farm10operational4.9
North Fossil Farmsolar farm40approved, not built4.9
Oaklands Plantationsolar farm5operational5.9
Galton Manor Solar Parksolar farm5operational6.2
Holly Farm Solar Parksolar farm5operational6.6
Galton Manor Farm Solar Farmsolar farm30approved, not built7.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.6886, -2.2235).