Energy Projects Near You

Solar, wind and battery projects near Wareham (BH20)

22 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of BH20 (Dorset): 9 approved but not yet running, 11 operational. The largest live scheme is North Fossil Farm (40 MW solar farm, approved on 12 January 2022, not yet built; REPD status may be out of date), 9.8 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

22projects within 10 km
0awaiting a decision
9approved, not running
11operational

Projects within 10 km of BH20

Projects of 1 MW and more (12)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Alaska Wind Farmwind farmwind farm9.2operationalupdated May 2026Nov 2009granted Jul 2012May 2026Dorset2.0
Oaklands Plantationsolar farmsolar farm5operationalupdated Jan 2017Jun 2014granted Nov 2014Jan 2017Dorset2.1
Stokeford Farmsolar farmsolar farm28.5operationalupdated Nov 2024Aug 2015granted Oct 2015Nov 2024Dorset2.1
Bottom Plainsolar farmsolar farm10operationalupdated Apr 2015Aug 2013granted Nov 2013Apr 2015Dorset3.0
Trigon Solar Farmsolar farmsolar farm7operationalupdated Apr 2013Jul 2012granted Nov 2012Apr 2013Dorset3.1
Woolbridge Solar Parksolar farmsolar farm5operationalupdated Aug 2017Aug 2013granted Dec 2013Aug 2017Dorset5.2
South Newton Farmsolar farmsolar farm11.3operationalupdated Jan 2017Mar 2013granted Jun 2013Jan 2017Dorset6.5
North of Newton Farmsolar farmsolar farm3operationalupdated Mar 2015Mar 2013granted Jun 2013Mar 2015Dorset7.5
Dolmans Hill (Redbridge Farm) Solar Arrayssolar farmsolar farm5operationalupdated Jan 2014Apr 2012granted Nov 2012Jan 2014Dorset7.7
Race farmsolar farmsolar farm6.1operationalupdated Jan 2017Mar 2013granted Jun 2013Jan 2017Dorset9.2
Post Farm, Lytchett Minsterbattery storagebattery storage32approved, not builtupdated Jan 2025May 2023granted Nov 2024Jan 2025Dorset9.5
North Fossil Farmsolar farmsolar farm40approved, not built may be out of dateupdated Feb 2022Jan 2021granted Jan 2022Feb 2022Dorset9.8
Smaller schemes under 1 MW, mostly rooftop solar (10)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
The Purbeck Schoolrooftop solarrooftop solar0.3approved, not builtupdated Jan 2022Sep 2021granted Nov 2021Jan 2022Dorset1.9
The Purbeck School, Worgret Roadrooftop solarrooftop solar0.1approved, not builtupdated May 2025Mar 2025granted Apr 2025May 2025Dorset1.9
Birchwood Tourist Park, Bere Roadsolar farmsolar farm0.2approved, not built may be out of dateupdated Jun 2023Jan 2023granted Jun 2023Jun 2023Dorset3.3
Sandford Road, Sandford Solar Photovoltaics PV Equipmentrooftop solarrooftop solar0.2approved, not builtupdated Jan 2022Nov 2021granted Jan 2022Jan 2022Dorset4.5
Sandford Holiday Park, Organford Roadrooftop solarrooftop solar0.2approved, not builtupdated Nov 2022Sep 2022granted Nov 2022Nov 2022Dorset5.5
Slepe Farmbattery storagebattery storage0.3operationalupdated Nov 2016Jun 2011granted Aug 2011Nov 2016Dorset6.7
Dorset Innovation Park, Newburghrooftop solarrooftop solar0.2approved, not builtupdated Sep 2025Jul 2025granted Aug 2025Sep 2025Dorset7.6
Lytchett Minster School, Post Green Roadrooftop solarrooftop solar0.3application withdrawnupdated May 2026Apr 2026—May 2026Dorset8.7
Rockley Park Caravan Holiday Park, Hamworthyrooftop solarrooftop solar0.3approved, not builtupdated Nov 2023Oct 2023granted Nov 2023Nov 2023Bournemouth, Christchurch and Poole9.0
Haven Rockley Holiday Park, Napier Roadrooftop solarrooftop solar0.5refusedupdated Jun 2023Jun 2023refused Aug 2023Jun 2023Bournemouth, Christchurch and Poole9.2

Distance from the average position of the BH20 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm11029040.2
Rooftop solar806011.3
Wind farm100100
Battery storage2011032

MW in pipeline: pending, approved and under-construction capacity.

How Dorset decides solar, wind and battery applications

ApplicationsDorsetUK
Decided applications (solar, wind, battery)12510,236
Refused23 (18%)19%
Solar refused15 of 10512%
Onshore wind refused5 of 545%
Battery storage refused3 of 1516%
Median time from submission to decision19.0 weeks17.0 weeks
Appeals lodged / allowed6 / 6—

All projects in Dorset

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near BH20, 2 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.