Energy Projects Near You

North Fossil Farm (40 MW solar farm)

North Fossil Farm is a 40 MW solar farm project in Dorset, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 12 January 2022, not yet built; the record was last updated on 16 February 2022. REPD records the planning permission as expiring on 12 January 2025, but the project holds a Contracts for Difference award (AR4), so construction may have started. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

40 MWsolar farm
approved, not builtmay be out of datestatus in REPD
16 February 2022record last updated
Dorsetcouncil area

REPD records the planning permission as expiring on 12 January 2025, but the project holds a Contracts for Difference award (AR4), so construction may have started.

Planning timeline

DateStage
21 January 2021Application submitted
12 January 2022Planning permission granted
12 January 2025Permission expired

Project details

Technology
solar farm
Capacity
40 MW
Status (REPD)
approved, not built
Record last updated
16 February 2022
Operator or applicant
Spring Dev 03 Ltd
Planning authority
Dorset
Planning application reference
6/2020/0595
Site area
47.5 ha
Address (REPD)
Land North of North Fossil Farm, Dorchester Road, East Knighton, Dorchester,
Council area (by location)
Dorset
Time to decision
51 weeks
Contracts for Difference
AR4
Name in REPD
North Fossil Farm - Solar Panels
REPD reference
8828

Who decides

ApplicationsDorsetUK
Decided applications (solar, wind, battery)12510,236
Refused23 (18%)19%
Solar refused15 of 10512%
Onshore wind refused5 of 545%
Battery storage refused3 of 1516%
Median time from submission to decision19.0 weeks17.0 weeks
Appeals lodged / allowed6 / 6—

Other large projects within 10 km

ProjectTypeMWStatuskm
Galton Manor Solar Parksolar farm5operational1.6
Galton Manor Farm Solar Farmsolar farm30approved, not built2.3
Land at East Farmsolar farm5operational2.8
Holly Farm Solar Parksolar farm5operational3.3
Crossways Pit Solar Farmsolar farm5operational4.6
Woolbridge Solar Parksolar farm5operational4.9
Stokeford Farmsolar farm28.5operational7.8
Alaska Wind Farmwind farm9.2operational7.8
Trigon Solar Farmsolar farm7operational9.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.6672, -2.2843).