Energy Projects Near You

Holly Farm Solar Park (5 MW)

Holly Farm Solar Park is a 5 MW solar farm project in Dorset, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 31 March 2017; the record was last updated on 23 June 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
23 June 2017record last updated
Dorsetcouncil area

Planning timeline

DateStage
29 July 2015Application submitted
18 December 2015Planning permission granted
20 January 2017Construction started
31 March 2017Operational

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
23 June 2017
Operator or applicant
British Solar Renewables
Planning authority
Dorset
Planning application reference
WD/D/15/001856
Site area
9.3 ha
Address (REPD)
Holly Farm, Moreton Road, Owermoigne, Dorchester,
Council area (by location)
Dorset
Time to decision
20 weeks
REPD reference
5632

Who decides

ApplicationsDorsetUK
Decided applications (solar, wind, battery)12510,236
Refused23 (18%)19%
Solar refused15 of 10512%
Onshore wind refused5 of 545%
Battery storage refused3 of 1516%
Median time from submission to decision19.0 weeks17.0 weeks
Appeals lodged / allowed6 / 6—

Other large projects within 10 km

ProjectTypeMWStatuskm
Crossways Pit Solar Farmsolar farm5operational1.4
Land at East Farmsolar farm5operational1.6
Galton Manor Solar Parksolar farm5operational2.1
Galton Manor Farm Solar Farmsolar farm30approved, not built2.5
North Fossil Farmsolar farm40approved, not built3.3
Woolbridge Solar Parksolar farm5operational6.6
West Dorset Wind Farmwind farm12.5application withdrawn7.9
Yellowham solar parksolar farm20refused on appeal8.0
Slyer's Lanewind farm18refused9.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.688, -2.3171).