Energy Projects Near You

Galton Manor Solar Park (5 MW)

Galton Manor Solar Park is a 5 MW solar farm project in Dorset, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 31 March 2017; the record was last updated on 23 June 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
23 June 2017record last updated
Dorsetcouncil area

Planning timeline

DateStage
14 July 2015Application submitted
7 September 2016Planning permission granted
20 January 2017Construction started
31 March 2017Operational

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
23 June 2017
Operator or applicant
British Solar Renewables
Planning authority
Dorset
Planning application reference
WD/D/15/001708
Address (REPD)
Land to North East of Galton Road, Galton, Dorchester
Council area (by location)
Dorset
Time to decision
60 weeks
REPD reference
5512

Who decides

ApplicationsDorsetUK
Decided applications (solar, wind, battery)12510,236
Refused23 (18%)19%
Solar refused15 of 10512%
Onshore wind refused5 of 545%
Battery storage refused3 of 1516%
Median time from submission to decision19.0 weeks17.0 weeks
Appeals lodged / allowed6 / 6—

Other large projects within 10 km

ProjectTypeMWStatuskm
Galton Manor Farm Solar Farmsolar farm30approved, not built0.9
Land at East Farmsolar farm5operational1.3
North Fossil Farmsolar farm40approved, not built1.6
Holly Farm Solar Parksolar farm5operational2.1
Crossways Pit Solar Farmsolar farm5operational3.6
Woolbridge Solar Parksolar farm5operational6.2
Stokeford Farmsolar farm28.5operational9.2
Alaska Wind Farmwind farm9.2operational9.2
West Dorset Wind Farmwind farm12.5application withdrawn9.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.6699, -2.3064).