North Farm, Horton Solar Farm (19 MW)

North Farm, Horton Solar Farm is a 19 MW solar farm project in Dorset, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 7 May 2025, not yet built; the record was last updated on 11 June 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

19 MWsolar farm
approved, not builtstatus in REPD
11 June 2025record last updated
Dorsetcouncil area

Planning timeline

DateStage
16 May 2023Application submitted
7 May 2025Planning permission granted
7 May 2030Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
19 MW
Status (REPD)
approved, not built
Record last updated
11 June 2025
Operator or applicant
North Farm Mannington Solar Limited / BayWa r.e.
Planning authority
Dorset
Planning application reference
P/FUL/2023/02829
Site area
29.8 ha
Address (REPD)
North Farm Horton
Council area (by location)
Dorset
Time to decision
103 weeks
Name in REPD
North Farm, Horton - Solar Farm
REPD reference
11698

Who decides

ApplicationsDorsetUK
Decided applications (solar, wind, battery)12510,236
Refused23 (18%)19%
Solar refused15 of 10512%
Onshore wind refused5 of 545%
Battery storage refused3 of 1516%
Median time from submission to decision19.0 weeks17.0 weeks
Appeals lodged / allowed6 / 6—

Other large projects within 10 km

ProjectTypeMWStatuskm
Woodlands Manor Farm, Horton Solar Farmsolar farm30approved, not built1.6
Wedgehill Farmsolar farm13operational4.3
Mannington Battery Energy Storage Systembattery storage49.9under construction5.1
Verwood Solar Farmsolar farm20.4operational5.3
Holt Roadbattery storage47.5approved, not built5.6
Bedborough Farmsolar farm7operational7.2
Homeland Solar Farmsolar farm13.2operational7.3
Warren Park Solar Farmsolar farm5permission expired8.6
Cross Roads Plantationsolar farm5operational8.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.8792, -1.9556).