Energy Projects Near You

Chapel Lane Parley Solar Farm Phase 1 (20 MW)

Chapel Lane Parley Solar Farm Phase 1 is a 20 MW solar farm project in Bournemouth, Christchurch and Poole, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 31 March 2014; the record was last updated on 22 September 2014.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

20 MWsolar farm
operationalstatus in REPD
22 September 2014record last updated
Bournemouth, Christchurch and Poolecouncil area

Planning timeline

DateStage
28 November 2012Application submitted
28 March 2013Planning permission granted
10 January 2014Construction started
31 March 2014Operational

Project details

Technology
solar farm
Capacity
20 MW
Status (REPD)
operational
Record last updated
22 September 2014
Operator or applicant
Solar Power Generation Limited
Planning authority
Bournemouth, Christchurch and Poole
Planning application reference
8/12/0512
Site area
76.7 ha
Address (REPD)
Parley (Adjacent to Ecos Sustainable Solutions Waste & Recycling Facility)
Council area (by location)
Bournemouth, Christchurch and Poole
Time to decision
17 weeks
REPD reference
2282

Who decides

ApplicationsBournemouth, Christchurch and PooleUK
Decided applications (solar, wind, battery)3010,236
Refused6 (20%)19%
Solar refused6 of 2812%
Battery storage refused0 of 216%
Median time from submission to decision10.6 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Parley Renewable Energy Park (PV)solar farm5refused0.4
Chapel Lane Parley Solar Farm Phase 2solar farm36operational0.6
Hale Farmsolar farm8operational1.5
Parley Court Solar Farmsolar farm35approved, not built2.5
Bedborough Farmsolar farm7operational5.3
Homeland Solar Farmsolar farm13.2operational6.1
Dorset Green Solar Farmsolar farm5operational6.8
Holt Roadbattery storage47.5approved, not built6.9
Mannington Battery Energy Storage Systembattery storage49.9under construction6.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.7918, -1.8612).