Hale Farm (8 MW solar farm)

Hale Farm is an 8 MW solar farm project in Dorset, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 26 February 2016; the record was last updated on 4 March 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

8 MWsolar farm
operationalstatus in REPD
4 March 2016record last updated
Dorsetcouncil area

Planning timeline

DateStage
28 October 2014Application submitted
23 September 2015Planning permission granted
26 February 2016Operational

Project details

Technology
solar farm
Capacity
8 MW
Status (REPD)
operational
Record last updated
4 March 2016
Operator or applicant
Hale Solar Limited
Planning authority
Bournemouth, Christchurch and Poole
Planning application reference
8/14/0520
Site area
18.7 ha
Address (REPD)
Hale Farm, Parley Green Lane, Christchurch
Council area (by location)
Dorset
Time to decision
47 weeks
REPD reference
4727

Who decides

ApplicationsBournemouth, Christchurch and PooleUK
Decided applications (solar, wind, battery)3010,236
Refused6 (20%)19%
Solar refused6 of 2812%
Battery storage refused0 of 216%
Median time from submission to decision10.6 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Parley Court Solar Farmsolar farm35approved, not built1.0
Chapel Lane Parley Solar Farm Phase 1solar farm20operational1.5
Parley Renewable Energy Park (PV)solar farm5refused1.7
Chapel Lane Parley Solar Farm Phase 2solar farm36operational2.0
Bedborough Farmsolar farm7operational6.1
Dorset Green Solar Farmsolar farm5operational6.2
Homeland Solar Farmsolar farm13.2operational7.6
Waterditch Farm Solar Farm & Battery Storagesolar farm49.9application submitted8.0
Waterditch Solar Farmsolar farm18operational8.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.7784, -1.864).