Christchurch Energy (18 MW solar farm)

Christchurch Energy is an 18 MW solar farm project in Bournemouth, Christchurch and Poole, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 27 March 2015; the record was last updated on 16 April 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

18 MWsolar farm
operationalstatus in REPD
16 April 2015record last updated
Bournemouth, Christchurch and Poolecouncil area

Planning timeline

DateStage
21 May 2014Application submitted
29 August 2014Planning permission granted
5 January 2015Construction started
27 March 2015Operational

Project details

Technology
solar farm
Capacity
18 MW
Status (REPD)
operational
Record last updated
16 April 2015
Operator or applicant
New Forest Energy Ltd
Planning authority
Bournemouth, Christchurch and Poole
Planning application reference
8/14/0226
Site area
45.0 ha
Address (REPD)
Land at East Close Farm Waterditch, Christchurch
Council area (by location)
Bournemouth, Christchurch and Poole
Time to decision
14 weeks
REPD reference
2308

Who decides

ApplicationsBournemouth, Christchurch and PooleUK
Decided applications (solar, wind, battery)3010,236
Refused6 (20%)19%
Solar refused6 of 2812%
Battery storage refused0 of 216%
Median time from submission to decision10.6 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Waterditch Solar Farmsolar farm18operational0.4
Waterditch Farm Solar Farm & Battery Storagesolar farm49.9application submitted0.9
Office Fieldsolar farm7.2operational3.3
Solar Farm at Walkford Moor Solar Farmsolar farm15approved, not built4.9
Parley Court Solar Farmsolar farm35approved, not built8.1
Hale Farmsolar farm8operational8.4
Parley Renewable Energy Park (PV)solar farm5refused8.5
Chapel Lane Parley Solar Farm Phase 2solar farm36operational8.7
Chapel Lane Parley Solar Farm Phase 1solar farm20operational8.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.7555, -1.7502).