Solar, wind and battery projects near New Milton (BH25)
15 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of BH25 (New Forest): 4 are waiting for a planning decision, 1 approved but not yet running, 6 operational. The largest live scheme is Waterditch Farm Solar Farm & Battery Storage (49.9 MW solar farm, application submitted on 21 July 2025, no decision recorded), 6.8 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of BH25
Projects of 1 MW and more (11)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Solar Farm at Walkford Moor Solar Farmsolar farm | solar farm | 15 | approved, not builtupdated Feb 2026 | Dec 2023 | granted Aug 2024 | Feb 2026 | New Forest | 1.6 |
| Beckley Solar Farmsolar farm | solar farm | 1.7 | operationalupdated May 2016 | Apr 2012 | granted Jun 2012 | May 2016 | New Forest | 1.8 |
| Office Fieldsolar farm | solar farm | 7.2 | operationalupdated Feb 2014 | Oct 2012 | granted Dec 2012 | Feb 2014 | New Forest | 3.2 |
| Limolands Farmsolar farm | solar farm | 5 | application withdrawnupdated Sep 2014 | Jun 2014 | — | Sep 2014 | New Forest | 3.3 |
| Limolands Farm Solar Arraysolar farm | solar farm | 5 | refused on appealupdated Apr 2016 | Oct 2014 | refused Dec 2014 | Apr 2016 | New Forest | 3.3 |
| Christchurch Energysolar farm | solar farm | 18 | operationalupdated Apr 2015 | May 2014 | granted Aug 2014 | Apr 2015 | Bournemouth, Christchurch and Poole | 6.5 |
| Waterditch Solar Farmsolar farm | solar farm | 18 | operationalupdated Mar 2016 | May 2015 | granted Jun 2015 | Mar 2016 | Bournemouth, Christchurch and Poole | 6.6 |
| Waterditch Farm Solar Farm & Battery Storagesolar farm | solar farm | 49.9 | application submittedupdated Sep 2025 | Jul 2025 | — | Sep 2025 | Bournemouth, Christchurch and Poole | 6.8 |
| Pennington Recycling Centresolar farm | solar farm | 1.2 | operationalupdated Aug 2016 | Jul 2015 | granted Sep 2015 | Aug 2016 | New Forest | 6.9 |
| Pennington Wastewater Treatment Works, Milford Roadsolar farm | solar farm | 1.3 | application submitted may be out of dateupdated May 2024 | Apr 2024 | — | May 2024 | New Forest | 7.0 |
| Lower Pennington Farmsolar farm | solar farm | 2.7 | operationalupdated Aug 2014 | Sep 2013 | granted Dec 2013 | Aug 2014 | New Forest | 7.5 |
Smaller schemes under 1 MW, mostly rooftop solar (4)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Hoburne Naish, Glenside Naish Estaterooftop solar | rooftop solar | 0.2 | refusedupdated Mar 2023 | Jan 2023 | refused Feb 2023 | Mar 2023 | New Forest | 2.5 |
| Christchurch Road, Downtonbattery storage | battery storage | 0.2 | refusedupdated Oct 2024 | Aug 2024 | refused Oct 2024 | Oct 2024 | New Forest | 3.3 |
| Christchurch Road, Downtonbattery storage | battery storage | 0.2 | application submittedupdated Jan 2025 | Jan 2025 | — | Jan 2025 | New Forest | 3.3 |
| Waterditch Farm Solar Farm & Battery Storagebattery storage | battery storage | — | application submittedupdated Sep 2025 | Jul 2025 | — | Sep 2025 | Bournemouth, Christchurch and Poole | 6.8 |
Distance from the average position of the BH25 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 11 | 2 | 1 | 6 | 1 | 66.2 |
| Rooftop solar | 1 | 0 | 0 | 0 | 1 | 0 |
| Battery storage | 3 | 2 | 0 | 0 | 1 | 0.2 |
MW in pipeline: pending, approved and under-construction capacity.
How New Forest decides solar, wind and battery applications
| Applications | New Forest | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 26 | 10,236 |
| Refused | 7 (27%) | 19% |
| Solar refused | 6 of 22 | 12% |
| Battery storage refused | 1 of 4 | 16% |
| Median time from submission to decision | 11.0 weeks | 17.0 weeks |
| Appeals lodged / allowed | 2 / 0 | — |
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near BH25, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.