Energy Projects Near You

Limolands Farm Solar Array (5 MW)

Limolands Farm Solar Array is a 5 MW solar farm project in New Forest, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 30 March 2016; the record was last updated on 4 April 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
refused on appealstatus in REPD
4 April 2016record last updated
New Forestcouncil area

Planning timeline

DateStage
3 October 2014Application submitted
17 December 2014Refused by the planning authority
15 May 2015Appeal lodged
30 March 2016Appeal refused

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
refused on appeal
Record last updated
4 April 2016
Operator or applicant
Locogen
Planning authority
New Forest
Planning application reference
14/00817
Appeal reference
APP/B9506/W/15/3006387
Site area
13.6 ha
Address (REPD)
Limolands Farm, Vaggs Lane, Hordle, Lymington
Council area (by location)
New Forest
Time to decision
11 weeks
REPD reference
4715

Who decides

ApplicationsNew ForestUK
Decided applications (solar, wind, battery)2610,236
Refused7 (27%)19%
Solar refused6 of 2212%
Battery storage refused1 of 416%
Median time from submission to decision11.0 weeks17.0 weeks
Appeals lodged / allowed2 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Limolands Farmsolar farm5application withdrawn<0.1
Solar Farm at Walkford Moor Solar Farmsolar farm15approved, not built4.7
Office Fieldsolar farm7.2operational6.1
Christchurch Energysolar farm18operational9.3
Waterditch Solar Farmsolar farm18operational9.4
Waterditch Farm Solar Farm & Battery Storagesolar farm49.9application submitted9.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.7694, -1.6196).