Energy Projects Near You

Office Field (7.2 MW solar farm)

Office Field is a 7.2 MW solar farm project in New Forest, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 28 March 2013; the record was last updated on 20 February 2014.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

7.2 MWsolar farm
operationalstatus in REPD
20 February 2014record last updated
New Forestcouncil area

Planning timeline

DateStage
15 October 2012Application submitted
11 December 2012Planning permission granted
28 March 2013Operational

Project details

Technology
solar farm
Capacity
7.2 MW
Status (REPD)
operational
Record last updated
20 February 2014
Operator or applicant
Anesco
Planning authority
New Forest
Planning application reference
12/99313
Site area
14.6 ha
Address (REPD)
Hinton, Bransgore, Hants
Council area (by location)
New Forest
Time to decision
8 weeks
REPD reference
1273

Who decides

ApplicationsNew ForestUK
Decided applications (solar, wind, battery)2610,236
Refused7 (27%)19%
Solar refused6 of 2212%
Battery storage refused1 of 416%
Median time from submission to decision11.0 weeks17.0 weeks
Appeals lodged / allowed2 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Solar Farm at Walkford Moor Solar Farmsolar farm15approved, not built1.6
Christchurch Energysolar farm18operational3.3
Waterditch Solar Farmsolar farm18operational3.4
Waterditch Farm Solar Farm & Battery Storagesolar farm49.9application submitted3.5
Limolands Farmsolar farm5application withdrawn6.1
Limolands Farm Solar Arraysolar farm5refused on appeal6.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.7569, -1.7037).