Energy Projects Near You

Limolands Farm (5 MW solar farm)

Limolands Farm is a 5 MW solar farm project in New Forest, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application withdrawn on 15 August 2014; the record was last updated on 19 September 2014.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
application withdrawnstatus in REPD
19 September 2014record last updated
New Forestcouncil area

Planning timeline

DateStage
11 June 2014Application submitted
15 August 2014Application withdrawn

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
application withdrawn
Record last updated
19 September 2014
Operator or applicant
Locogen
Planning authority
New Forest
Planning application reference
14/00470
Site area
13.6 ha
Address (REPD)
Limolands Farm, Vaggs Lane, Hordle, Lymington
Council area (by location)
New Forest
REPD reference
2147

Who decides

ApplicationsNew ForestUK
Decided applications (solar, wind, battery)2610,236
Refused7 (27%)19%
Solar refused6 of 2212%
Battery storage refused1 of 416%
Median time from submission to decision11.0 weeks17.0 weeks
Appeals lodged / allowed2 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Limolands Farm Solar Arraysolar farm5refused on appeal<0.1
Solar Farm at Walkford Moor Solar Farmsolar farm15approved, not built4.7
Office Fieldsolar farm7.2operational6.1
Christchurch Energysolar farm18operational9.3
Waterditch Solar Farmsolar farm18operational9.4
Waterditch Farm Solar Farm & Battery Storagesolar farm49.9application submitted9.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.7694, -1.6196).