Energy Projects Near You

Solar, wind and battery projects near Totland Bay (PO39)

12 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of PO39 (Isle of Wight): 2 are waiting for a planning decision, 1 approved but not yet running, 6 operational. The largest live scheme is Solar PV Panels (30 MW solar farm, approved on 8 September 2023, not yet built), 4.5 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

12projects within 10 km
2awaiting a decision
1approved, not running
6operational

Projects within 10 km of PO39

Projects of 1 MW and more (10)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Wilmingham Lane Solar Farmsolar farmsolar farm7operationalupdated Apr 2013Jan 2012granted Apr 2012Apr 2013Isle of Wight3.9
Solar PV Panelssolar farmsolar farm30approved, not builtupdated Sep 2023Oct 2022granted Sep 2023Sep 2023Isle of Wight4.5
Wellow Wind Farmwind farmwind farm12refusedupdated Jul 2006May 2006refused Nov 2006Jul 2006Isle of Wight5.3
Vectis wind farmwind farmwind farm12.5refusedupdated May 2013Jul 2011refused Jul 2012May 2013Isle of Wight6.1
Lee Farmsolar farmsolar farm5operationalupdated Jan 2014Feb 2011granted Apr 2011Jan 2014Isle of Wight6.6
Pennington Recycling Centresolar farmsolar farm1.2operationalupdated Aug 2016Jul 2015granted Sep 2015Aug 2016New Forest6.7
Lower Pennington Farmsolar farmsolar farm2.7operationalupdated Aug 2014Sep 2013granted Dec 2013Aug 2014New Forest6.7
Pennington Wastewater Treatment Works, Milford Roadsolar farmsolar farm1.3application submitted may be out of dateupdated May 2024Apr 2024—May 2024New Forest6.9
Homestead Farmsolar farmsolar farm10.7operationalupdated Mar 2016May 2014granted Oct 2014Mar 2016Isle of Wight7.0
Stables Farmsolar farmsolar farm1.5operationalupdated Mar 2013Mar 2012granted Jun 2012Mar 2013Isle of Wight8.5
Smaller schemes under 1 MW, mostly rooftop solar (2)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Christchurch Road, Downtonbattery storagebattery storage0.2refusedupdated Oct 2024Aug 2024refused Oct 2024Oct 2024New Forest8.6
Christchurch Road, Downtonbattery storagebattery storage0.2application submittedupdated Jan 2025Jan 2025—Jan 2025New Forest8.6

Distance from the average position of the PO39 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm8116031.3
Wind farm200020
Battery storage210010.2

MW in pipeline: pending, approved and under-construction capacity.

How Isle of Wight decides solar, wind and battery applications

ApplicationsIsle of WightUK
Decided applications (solar, wind, battery)2510,236
Refused5 (20%)19%
Solar refused0 of 1712%
Onshore wind refused5 of 645%
Battery storage refused0 of 216%
Median time from submission to decision16.6 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

All projects in Isle of Wight

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near PO39, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.