Vectis wind farm (12.5 MW)

Vectis wind farm is a 12.5 MW wind farm project in Isle of Wight, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 23 July 2012; the record was last updated on 17 May 2013.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

12.5 MWwind farm
refusedstatus in REPD
17 May 2013record last updated
Isle of Wightcouncil area

Planning timeline

DateStage
15 July 2011Application submitted
23 July 2012Refused by the planning authority

Project details

Technology
wind farm
Capacity
12.5 MW
Status (REPD)
refused
Record last updated
17 May 2013
Operator or applicant
Infinergy
Planning authority
Isle of Wight
Planning application reference
P/00706/11
Turbines
5
Address (REPD)
Vectis wind farm, land south of Wellow/east of Holmfield Avenue west of Stoneovers and off Broad Lane Shalcombe Yarmouth Isle Of Wight PO41
Council area (by location)
Isle of Wight
Time to decision
53 weeks
REPD reference
3755

Who decides

ApplicationsIsle of WightUK
Decided applications (solar, wind, battery)2510,236
Refused5 (20%)19%
Solar refused0 of 1712%
Onshore wind refused5 of 645%
Battery storage refused0 of 216%
Median time from submission to decision16.6 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Wellow Wind Farmwind farm12refused0.9
Lee Farmsolar farm5operational1.2
Homestead Farmsolar farm10.7operational1.5
Solar PV Panelssolar farm30approved, not built2.3
Wilmingham Lane Solar Farmsolar farm7operational2.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.6825, -1.4533).