Wellow Wind Farm (12 MW)
Wellow Wind Farm is a 12 MW wind farm project in Isle of Wight, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 2 November 2006; the record was last updated on 5 July 2006.
12 MWwind farm
refusedstatus in REPD
5 July 2006record last updated
Isle of Wightcouncil area
Planning timeline
| Date | Stage |
|---|---|
| 26 May 2006 | Application submitted |
| 2 November 2006 | Refused by the planning authority |
Project details
- Technology
- wind farm
- Capacity
- 12 MW
- Status (REPD)
- refused
- Record last updated
- 5 July 2006
- Operator or applicant
- Your Energy
- Planning authority
- Isle of Wight
- Planning application reference
- not recorded
- Turbines
- 6
- Address (REPD)
- Wellow West Wight Isle of Wight
- Council area (by location)
- Isle of Wight
- Time to decision
- 23 weeks
- REPD reference
- 3115
Who decides
| Applications | Isle of Wight | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 25 | 10,236 |
| Refused | 5 (20%) | 19% |
| Solar refused | 0 of 17 | 12% |
| Onshore wind refused | 5 of 6 | 45% |
| Battery storage refused | 0 of 2 | 16% |
| Median time from submission to decision | 16.6 weeks | 17.0 weeks |
| Appeals lodged / allowed | 0 / 0 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Vectis wind farm | wind farm | 12.5 | refused | 0.9 |
| Wilmingham Lane Solar Farm | solar farm | 7 | operational | 1.4 |
| Solar PV Panels | solar farm | 30 | approved, not built | 1.5 |
| Lee Farm | solar farm | 5 | operational | 1.5 |
| Homestead Farm | solar farm | 10.7 | operational | 1.9 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.6846, -1.4656).