Lee Farm (5 MW solar farm)

Lee Farm is a 5 MW solar farm project in Isle of Wight, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 31 July 2012; the record was last updated on 23 January 2014.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
23 January 2014record last updated
Isle of Wightcouncil area

Planning timeline

DateStage
7 February 2011Application submitted
14 April 2011Planning permission granted
31 July 2012Operational

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
23 January 2014
Operator or applicant
Vogt Solar
Planning authority
Isle of Wight
Planning application reference
P/00168/11
Site area
15.3 ha
Address (REPD)
Main Road, Wellow, Yarmouth, Isle Of Wight
Council area (by location)
Isle of Wight
Time to decision
9 weeks
REPD reference
1558

Who decides

ApplicationsIsle of WightUK
Decided applications (solar, wind, battery)2510,236
Refused5 (20%)19%
Solar refused0 of 1712%
Onshore wind refused5 of 645%
Battery storage refused0 of 216%
Median time from submission to decision16.6 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Homestead Farmsolar farm10.7operational0.5
Vectis wind farmwind farm12.5refused1.2
Wellow Wind Farmwind farm12refused1.5
Solar PV Panelssolar farm30approved, not built2.2
Wilmingham Lane Solar Farmsolar farm7operational2.6
Camp Hill Wind Farmwind farm6refused9.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.6925, -1.4491).