Camp Hill Wind Farm (6 MW)
Camp Hill Wind Farm is a 6 MW wind farm project in Isle of Wight, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 18 December 2014; the record was last updated on 8 January 2014.
6 MWwind farm
refusedstatus in REPD
8 January 2014record last updated
Isle of Wightcouncil area
Planning timeline
| Date | Stage |
|---|---|
| 11 October 2013 | Application submitted |
| 18 December 2014 | Refused by the planning authority |
Project details
- Technology
- wind farm
- Capacity
- 6 MW
- Status (REPD)
- refused
- Record last updated
- 8 January 2014
- Operator or applicant
- Partnerships for Renewables
- Planning authority
- Isle of Wight
- Planning application reference
- P/00491/12
- Turbines
- 2
- Address (REPD)
- land at HMP Camp Hill Parkhurst Road Newport Isle Of Wight
- Council area (by location)
- Isle of Wight
- Time to decision
- 62 weeks
- REPD reference
- 4553
Who decides
| Applications | Isle of Wight | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 25 | 10,236 |
| Refused | 5 (20%) | 19% |
| Solar refused | 0 of 17 | 12% |
| Onshore wind refused | 5 of 6 | 45% |
| Battery storage refused | 0 of 2 | 16% |
| Median time from submission to decision | 16.6 weeks | 17.0 weeks |
| Appeals lodged / allowed | 0 / 0 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Grange Farm | solar farm | 6 | operational | 3.9 |
| Sunny Oaks Renewable Energy Park | battery storage | 28.5 | approved, not built | 4.8 |
| Sunny Oaks Renewable Energy Park | solar farm | 20 | approved, not built | 4.8 |
| Fieldscale | solar farm | 10.6 | operational | 6.6 |
| Homestead Farm | solar farm | 10.7 | operational | 9.3 |
| Exbury Solar Farm | solar farm | 5 | refused on appeal | 9.4 |
| Lee Farm | solar farm | 5 | operational | 9.8 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.7163, -1.3158).