Energy Projects Near You

Renewable energy projects in Isle of Wight

25 solar, wind or battery projects of 150 kW or more are located in Isle of Wight (REPD, July 2026 extract): 2 pending, 7 approved but not running, 11 operational and 4 refused. The council refused 5 of 25 decided applications (20%; UK 19%), with a median 17 weeks from submission to decision.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

25projects in the council area
2awaiting a decision
7approved, not running
20%of decisions refused

How Isle of Wight decides

ApplicationsIsle of WightUK
Decided applications (solar, wind, battery)2510,236
Refused5 (20%)19%
Solar refused0 of 1712%
Onshore wind refused5 of 645%
Battery storage refused0 of 216%
Median time from submission to decision16.6 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Projects in Isle of Wight

Projects of 1 MW and more (21)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updated
Solar PV Panelssolar farmsolar farm30approved, not builtupdated Sep 2023Oct 2022granted Sep 2023Sep 2023
Sunny Oaks Renewable Energy Parkbattery storagebattery storage28.5approved, not builtupdated Feb 2026Sep 2022granted Jul 2025Feb 2026
Sunny Oaks Renewable Energy Parksolar farmsolar farm20approved, not builtupdated Feb 2026Sep 2022granted Jul 2025Feb 2026
Vectis wind farmwind farmwind farm12.5refusedupdated May 2013Jul 2011refused Jul 2012May 2013
Wellow Wind Farmwind farmwind farm12refusedupdated Jul 2006May 2006refused Nov 2006Jul 2006
Homestead Farmsolar farmsolar farm10.7operationalupdated Mar 2016May 2014granted Oct 2014Mar 2016
Fieldscalesolar farmsolar farm10.6operationalupdated Jul 2016Aug 2014granted Oct 2014Jul 2016
Hill Farm Solar Parksolar farmsolar farm10.2operationalupdated Jul 2014Oct 2012granted Jan 2013Jul 2014
East Fairleesolar farmsolar farm7.3operationalupdated May 2015Jun 2013granted Oct 2013May 2015
Wilmingham Lane Solar Farmsolar farmsolar farm7operationalupdated Apr 2013Jan 2012granted Apr 2012Apr 2013
Grange Farmsolar farmsolar farm6operationalupdated Aug 2015Mar 2014granted Jun 2014Aug 2015
Camp Hill Wind Farmwind farmwind farm6refusedupdated Jan 2014Oct 2013refused Dec 2014Jan 2014
Lee Farmsolar farmsolar farm5operationalupdated Jan 2014Feb 2011granted Apr 2011Jan 2014
Ventnor Road Solar Parksolar farmsolar farm4.8operationalupdated Jun 2013Oct 2012granted Dec 2012Jun 2013
Durrants Farm Solarsolar farmsolar farm4.5operationalupdated Sep 2015Dec 2010granted Feb 2011Sep 2015
Cheverton Downwind farmwind farm3.9refusedupdated Dec 2009Jan 2009refused Dec 2009Dec 2009
Chawton Farm Solar Farmsolar farmsolar farm3.2operationalupdated Jun 2013Oct 2012granted Dec 2012Jun 2013
Newnham Farmsolar farmsolar farm2permission expiredupdated Jul 2016Mar 2011granted May 2011Jul 2016
Stables Farmsolar farmsolar farm1.5operationalupdated Mar 2013Mar 2012granted Jun 2012Mar 2013
Gkn & Whippingham Technology Park, Beatrice Avenuesolar farmsolar farm1.3approved, not builtupdated Nov 2023Apr 2023granted Oct 2023Nov 2023
Arreton Valley Nursery, Hale Commonbattery storagebattery storage1.3approved, not built may be out of dateupdated Aug 2023May 2023granted Jul 2023Aug 2023
Smaller schemes under 1 MW, mostly rooftop solar (4)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updated
Morrisons Supermarket, South Street Solar Photovoltaicsrooftop solarrooftop solar0.4application submitted may be out of dateupdated Nov 2022Oct 2022—Nov 2022
Bae Systems, Newport Roadsolar farmsolar farm0.3application submittedupdated Mar 2025Feb 2025—Mar 2025
Christ The King Upper College, Wellington Roadrooftop solarrooftop solar0.3approved, not builtupdated Jun 2026Apr 2026granted May 2026Jun 2026
The Island Free School, Newport Roadrooftop solarrooftop solar0.2approved, not builtupdated Jan 2026Oct 2025granted Dec 2025Jan 2026

Postcode districts in Isle of Wight

DistrictProjects within 10 kmPendingApprovedOperational
PO3019258
PO3115246
PO3216246
PO3316186
PO3413192
PO354003
PO3610045
PO377024
PO384022
PO3912216
PO4012216
PO4113127

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Projects belong to Isle of Wight by location (nearest postcode to the REPD grid reference); decisions are counted by the planning authority named in REPD.