Hill Farm Solar Park (10.2 MW)

Hill Farm Solar Park is a 10.2 MW solar farm project in Isle of Wight, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 30 May 2014; the record was last updated on 3 July 2014.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

10.2 MWsolar farm
operationalstatus in REPD
3 July 2014record last updated
Isle of Wightcouncil area

Planning timeline

DateStage
5 October 2012Application submitted
29 January 2013Planning permission granted
30 May 2014Operational

Project details

Technology
solar farm
Capacity
10.2 MW
Status (REPD)
operational
Record last updated
3 July 2014
Operator or applicant
Lightsource Renewable Energy (BNRG Renewables)
Planning authority
Isle of Wight
Planning application reference
P/01485/12
Site area
8.3 ha
Address (REPD)
Hill Farm, Carpenters Road, Brading, Ryde, Isle of Wight, PO33 1YN
Council area (by location)
Isle of Wight
Time to decision
17 weeks
REPD reference
1758

Who decides

ApplicationsIsle of WightUK
Decided applications (solar, wind, battery)2510,236
Refused5 (20%)19%
Solar refused0 of 1712%
Onshore wind refused5 of 645%
Battery storage refused0 of 216%
Median time from submission to decision16.6 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
East Fairleesolar farm7.3operational1.5
Fieldscalesolar farm10.6operational8.3
Sunny Oaks Renewable Energy Parkbattery storage28.5approved, not built8.5
Sunny Oaks Renewable Energy Parksolar farm20approved, not built8.5
Grange Farmsolar farm6operational9.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.6975, -1.1322).