Solar, wind and battery projects near Seaview (PO34)
13 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of PO34 (Isle of Wight): 1 is waiting for a planning decision, 9 approved but not yet running, 2 operational. The largest live scheme is Sunny Oaks Renewable Energy Park (28.5 MW battery storage, approved on 15 July 2025, not yet built), 9.5 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of PO34
Projects of 1 MW and more (5)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| East Fairleesolar farm | solar farm | 7.3 | operationalupdated May 2015 | Jun 2013 | granted Oct 2013 | May 2015 | Isle of Wight | 1.8 |
| Hill Farm Solar Parksolar farm | solar farm | 10.2 | operationalupdated Jul 2014 | Oct 2012 | granted Jan 2013 | Jul 2014 | Isle of Wight | 2.4 |
| Newnham Farmsolar farm | solar farm | 2 | permission expiredupdated Jul 2016 | Mar 2011 | granted May 2011 | Jul 2016 | Isle of Wight | 6.2 |
| Sunny Oaks Renewable Energy Parkbattery storage | battery storage | 28.5 | approved, not builtupdated Feb 2026 | Sep 2022 | granted Jul 2025 | Feb 2026 | Isle of Wight | 9.5 |
| Sunny Oaks Renewable Energy Parksolar farm | solar farm | 20 | approved, not builtupdated Feb 2026 | Sep 2022 | granted Jul 2025 | Feb 2026 | Isle of Wight | 9.5 |
Smaller schemes under 1 MW, mostly rooftop solar (8)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Immigration Removal Centre, Dolphin Wayrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Feb 2024 | Jan 2024 | granted Mar 2024 | Feb 2024 | Gosport | 7.4 |
| Qinetiq Haslar, Haslar Roadsolar farm | solar farm | 0.7 | approved, not built may be out of dateupdated Jun 2023 | Feb 2023 | granted Jun 2023 | Jun 2023 | Gosport | 7.9 |
| Walpole Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Dec 2022 | Oct 2022 | granted Dec 2022 | Dec 2022 | Gosport | 8.9 |
| Gunwharf Quays Shopping Centrerooftop solar | rooftop solar | 0.6 | approved, not built may be out of dateupdated Jul 2023 | Jan 2023 | granted Jun 2023 | Jul 2023 | Portsmouth | 8.9 |
| Ark Charter Academy, Hyde Park Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Aug 2025 | Jun 2025 | granted Jul 2025 | Aug 2025 | Portsmouth | 9.2 |
| Big Yellow Self Storage, Rodney Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Nov 2022 | Sep 2022 | granted Oct 2022 | Nov 2022 | Portsmouth | 9.9 |
| St Marys Hospital, Milton Road -Solar Panelsrooftop solar | rooftop solar | 0.5 | application submittedupdated Jan 2026 | Dec 2025 | — | Jan 2026 | Portsmouth | 10.0 |
| St Marys Hospital, Milton Roadrooftop solar | rooftop solar | 0.5 | approved, not builtupdated May 2026 | Jan 2026 | granted Mar 2026 | May 2026 | Portsmouth | 10.0 |
Distance from the average position of the PO34 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 5 | 0 | 2 | 2 | 0 | 20.7 |
| Rooftop solar | 7 | 1 | 6 | 0 | 0 | 2.3 |
| Battery storage | 1 | 0 | 1 | 0 | 0 | 28.5 |
MW in pipeline: pending, approved and under-construction capacity.
How Isle of Wight decides solar, wind and battery applications
| Applications | Isle of Wight | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 25 | 10,236 |
| Refused | 5 (20%) | 19% |
| Solar refused | 0 of 17 | 12% |
| Onshore wind refused | 5 of 6 | 45% |
| Battery storage refused | 0 of 2 | 16% |
| Median time from submission to decision | 16.6 weeks | 17.0 weeks |
| Appeals lodged / allowed | 0 / 0 | — |
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near PO34, 2 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.