Energy Projects Near You

Sunny Oaks Renewable Energy Park (20 MW)

Sunny Oaks Renewable Energy Park is a 20 MW solar farm project in Isle of Wight, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 15 July 2025, not yet built; the record was last updated on 20 February 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

20 MWsolar farm
approved, not builtstatus in REPD
20 February 2026record last updated
Isle of Wightcouncil area

Planning timeline

DateStage
5 September 2022Application submitted
15 July 2025Planning permission granted
15 July 2028Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
20 MW
Status (REPD)
approved, not built
Record last updated
20 February 2026
Operator or applicant
Ridge Clean Energy Limited
Planning authority
Isle of Wight
Planning application reference
22/01585/FUL
Site area
32.5 ha
Address (REPD)
Se/O Whiterails Road, W/O Briddlesford Road, Wootton, Ryde
Council area (by location)
Isle of Wight
Time to decision
149 weeks
Contracts for Difference
AR7a
REPD reference
12414

Who decides

ApplicationsIsle of WightUK
Decided applications (solar, wind, battery)2510,236
Refused5 (20%)19%
Solar refused0 of 1712%
Onshore wind refused5 of 645%
Battery storage refused0 of 216%
Median time from submission to decision16.6 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Sunny Oaks Renewable Energy Parkbattery storage28.5approved, not built<0.1
Grange Farmsolar farm6operational0.9
Fieldscalesolar farm10.6operational4.4
Camp Hill Wind Farmwind farm6refused4.8
East Fairleesolar farm7.3operational7.8
Hill Farm Solar Parksolar farm10.2operational8.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.7171, -1.2482).