Energy Projects Near You

Solar, wind and battery projects near Shanklin (PO37)

7 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of PO37 (Isle of Wight): 2 approved but not yet running, 4 operational. The largest live scheme is Arreton Valley Nursery, Hale Common (1.3 MW battery storage, approved on 31 July 2023, not yet built; REPD status may be out of date), 4.5 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

7projects within 10 km
0awaiting a decision
2approved, not running
4operational

Projects within 10 km of PO37

Projects of 1 MW and more (6)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Ventnor Road Solar Parksolar farmsolar farm4.8operationalupdated Jun 2013Oct 2012granted Dec 2012Jun 2013Isle of Wight2.1
Arreton Valley Nursery, Hale Commonbattery storagebattery storage1.3approved, not built may be out of dateupdated Aug 2023May 2023granted Jul 2023Aug 2023Isle of Wight4.5
Fieldscalesolar farmsolar farm10.6operationalupdated Jul 2016Aug 2014granted Oct 2014Jul 2016Isle of Wight6.9
Hill Farm Solar Parksolar farmsolar farm10.2operationalupdated Jul 2014Oct 2012granted Jan 2013Jul 2014Isle of Wight8.1
East Fairleesolar farmsolar farm7.3operationalupdated May 2015Jun 2013granted Oct 2013May 2015Isle of Wight9.3
Newnham Farmsolar farmsolar farm2permission expiredupdated Jul 2016Mar 2011granted May 2011Jul 2016Isle of Wight10.0
Smaller schemes under 1 MW, mostly rooftop solar (1)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
The Island Free School, Newport Roadrooftop solarrooftop solar0.2approved, not builtupdated Jan 2026Oct 2025granted Dec 2025Jan 2026Isle of Wight4.5

Distance from the average position of the PO37 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm500400
Rooftop solar101000.2
Battery storage101001.3

MW in pipeline: pending, approved and under-construction capacity.

How Isle of Wight decides solar, wind and battery applications

ApplicationsIsle of WightUK
Decided applications (solar, wind, battery)2510,236
Refused5 (20%)19%
Solar refused0 of 1712%
Onshore wind refused5 of 645%
Battery storage refused0 of 216%
Median time from submission to decision16.6 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

All projects in Isle of Wight

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near PO37, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.