Energy Projects Near You

Wilmingham Lane Solar Farm (7 MW)

Wilmingham Lane Solar Farm is a 7 MW solar farm project in Isle of Wight, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 14 March 2013; the record was last updated on 11 April 2013.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

7 MWsolar farm
operationalstatus in REPD
11 April 2013record last updated
Isle of Wightcouncil area

Planning timeline

DateStage
27 January 2012Application submitted
12 April 2012Planning permission granted
16 November 2012Construction started
14 March 2013Operational

Project details

Technology
solar farm
Capacity
7 MW
Status (REPD)
operational
Record last updated
11 April 2013
Operator or applicant
Low Carbon Solar
Planning authority
Isle of Wight
Planning application reference
P/00053/12
Site area
11.7 ha
Address (REPD)
Btw Tapnell Furze And Wilmingham Plantation, Wilmingham Lane, Freshwater, Isle of Wight, PO40 9UQ
Council area (by location)
Isle of Wight
Time to decision
11 weeks
REPD reference
1343

Who decides

ApplicationsIsle of WightUK
Decided applications (solar, wind, battery)2510,236
Refused5 (20%)19%
Solar refused0 of 1712%
Onshore wind refused5 of 645%
Battery storage refused0 of 216%
Median time from submission to decision16.6 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Solar PV Panelssolar farm30approved, not built0.9
Wellow Wind Farmwind farm12refused1.4
Vectis wind farmwind farm12.5refused2.3
Lee Farmsolar farm5operational2.6
Homestead Farmsolar farm10.7operational3.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.6872, -1.4855).