Energy Projects Near You

Solar, wind and battery projects near Yarmouth (PO41)

13 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of PO41 (Isle of Wight): 1 is waiting for a planning decision, 2 approved but not yet running, 7 operational. The largest live scheme is Solar PV Panels (30 MW solar farm, approved on 8 September 2023, not yet built), 0.8 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

13projects within 10 km
1awaiting a decision
2approved, not running
7operational

Projects within 10 km of PO41

Projects of 1 MW and more (12)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Solar PV Panelssolar farmsolar farm30approved, not builtupdated Sep 2023Oct 2022granted Sep 2023Sep 2023Isle of Wight0.8
Wilmingham Lane Solar Farmsolar farmsolar farm7operationalupdated Apr 2013Jan 2012granted Apr 2012Apr 2013Isle of Wight1.7
Wellow Wind Farmwind farmwind farm12refusedupdated Jul 2006May 2006refused Nov 2006Jul 2006Isle of Wight1.9
Lee Farmsolar farmsolar farm5operationalupdated Jan 2014Feb 2011granted Apr 2011Jan 2014Isle of Wight2.1
Homestead Farmsolar farmsolar farm10.7operationalupdated Mar 2016May 2014granted Oct 2014Mar 2016Isle of Wight2.4
Vectis wind farmwind farmwind farm12.5refusedupdated May 2013Jul 2011refused Jul 2012May 2013Isle of Wight2.6
Stables Farmsolar farmsolar farm1.5operationalupdated Mar 2013Mar 2012granted Jun 2012Mar 2013Isle of Wight3.8
Lower Pennington Farmsolar farmsolar farm2.7operationalupdated Aug 2014Sep 2013granted Dec 2013Aug 2014New Forest7.0
Pennington Recycling Centresolar farmsolar farm1.2operationalupdated Aug 2016Jul 2015granted Sep 2015Aug 2016New Forest7.5
Pennington Wastewater Treatment Works, Milford Roadsolar farmsolar farm1.3application submitted may be out of dateupdated May 2024Apr 2024—May 2024New Forest7.5
Durrants Farm Solarsolar farmsolar farm4.5operationalupdated Sep 2015Dec 2010granted Feb 2011Sep 2015Isle of Wight7.7
Cheverton Downwind farmwind farm3.9refusedupdated Dec 2009Jan 2009refused Dec 2009Dec 2009Isle of Wight8.7
Smaller schemes under 1 MW, mostly rooftop solar (1)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Newtown Park House Energy Centresolar farmsolar farm0.2approved, not built may be out of dateupdated Mar 2023Nov 2022granted Feb 2023Mar 2023New Forest8.6

Distance from the average position of the PO41 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm10127031.5
Wind farm300030

MW in pipeline: pending, approved and under-construction capacity.

How Isle of Wight decides solar, wind and battery applications

ApplicationsIsle of WightUK
Decided applications (solar, wind, battery)2510,236
Refused5 (20%)19%
Solar refused0 of 1712%
Onshore wind refused5 of 645%
Battery storage refused0 of 216%
Median time from submission to decision16.6 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

All projects in Isle of Wight

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near PO41, 2 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.