Homestead Farm (10.7 MW solar farm)

Homestead Farm is a 10.7 MW solar farm project in Isle of Wight, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 15 December 2015; the record was last updated on 15 March 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

10.7 MWsolar farm
operationalstatus in REPD
15 March 2016record last updated
Isle of Wightcouncil area

Planning timeline

DateStage
20 May 2014Application submitted
21 October 2014Planning permission granted
15 September 2015Construction started
15 December 2015Operational

Project details

Technology
solar farm
Capacity
10.7 MW
Status (REPD)
operational
Record last updated
15 March 2016
Operator or applicant
Anesco
Planning authority
Isle of Wight
Planning application reference
P/00607/14
Site area
19.0 ha
Address (REPD)
land at Homestead Farm, Caulbourne Lane AND land at Lower Dodpits Farm, Warlands Lane, Ningwood, Newport
Council area (by location)
Isle of Wight
Time to decision
22 weeks
REPD reference
2314

Who decides

ApplicationsIsle of WightUK
Decided applications (solar, wind, battery)2510,236
Refused5 (20%)19%
Solar refused0 of 1712%
Onshore wind refused5 of 645%
Battery storage refused0 of 216%
Median time from submission to decision16.6 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Lee Farmsolar farm5operational0.5
Vectis wind farmwind farm12.5refused1.5
Wellow Wind Farmwind farm12refused1.9
Solar PV Panelssolar farm30approved, not built2.6
Wilmingham Lane Solar Farmsolar farm7operational3.1
Camp Hill Wind Farmwind farm6refused9.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.694, -1.4431).