Energy Projects Near You

Salisbury Substation (49.5 MW battery storage)

Salisbury Substation is a 49.5 MW battery storage project in Wiltshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 April 2024; the record was last updated on 4 June 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.5 MWbattery storage
operationalstatus in REPD
4 June 2026record last updated
Wiltshirecouncil area

Planning timeline

DateStage
5 August 2019Application submitted
3 December 2021Planning permission granted
1 September 2022Construction started
1 April 2024Operational

Project details

Technology
battery storage (stand-alone storage)
Capacity
49.5 MW
Status (REPD)
operational
Record last updated
4 June 2026
Operator or applicant
SSE Renewables
Planning authority
Wiltshire
Planning application reference
19/05443/FUL
Address (REPD)
Land Adjacent To, Salisbury Substation, Wilton, Salisbury,
Council area (by location)
Wiltshire
Time to decision
122 weeks
REPD reference
7510

Who decides

ApplicationsWiltshireUK
Decided applications (solar, wind, battery)14010,236
Refused18 (13%)19%
Solar refused13 of 11012%
Onshore wind refused1 of 145%
Battery storage refused4 of 2916%
Median time from submission to decision20.9 weeks17.0 weeks
Appeals lodged / allowed5 / 7—

Other large projects within 10 km

ProjectTypeMWStatuskm
Bake Farmsolar farm16.1application withdrawn4.0
Bake Farm Solar Farmsolar farm5operational4.0
Beech Tree Solar Farmsolar farm30approved, not built4.4
Blackthorn Solar Farmsolar farm40application submitted9.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.082, -1.8522).