Energy Projects Near You

Solar, wind and battery projects near Salisbury (SP4)

11 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of SP4 (Wiltshire): 2 are waiting for a planning decision, 4 approved but not yet running, 3 operational. The largest live scheme is Down Barn Farm (49.9 MW solar farm, approved on 23 April 2020, not yet built; REPD status may be out of date), 6.4 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

11projects within 10 km
2awaiting a decision
4approved, not running
3operational

Projects within 10 km of SP4

Projects of 1 MW and more (5)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Boscombe Airfieldsolar farmsolar farm12.3operationalupdated Apr 2015Jun 2014granted Nov 2014Apr 2015Wiltshire2.5
Blackthorn Solar Farmsolar farmsolar farm40application submittedupdated Jun 2025May 2025—Jun 2025Wiltshire2.8
Down Barn Farmsolar farmsolar farm49.9approved, not built may be out of dateupdated May 2023Nov 2019granted Apr 2020May 2023Wiltshire6.4
Parkhouse Corner (Orta Solar)solar farmsolar farm6.6operationalupdated Apr 2013Aug 2012granted Nov 2012Apr 2013Test Valley7.1
Shipton Bellinger - Park House Corner Solar Farmsolar farmsolar farm5.4operationalupdated Apr 2013Mar 2011granted May 2011Apr 2013Test Valley7.7
Smaller schemes under 1 MW, mostly rooftop solar (6)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Ratfyn Water Recycling Centre, Amesburyrooftop solarrooftop solar0.3approved, not builtupdated Oct 2022Aug 2022granted Oct 2022Oct 2022Wiltshire1.7
Blackthorn Solar Farmbattery storagebattery storage—application submittedupdated Jun 2025May 2025—Jun 2025Wiltshire2.8
Chemring Countermeasures Limited, High Post Road- Solar Arrayrooftop solarrooftop solar—approved, not builtupdated Jul 2024Jun 2023granted Jun 2024Jul 2024Wiltshire4.5
Chemring Countermeasures Limited, Nettonrooftop solarrooftop solar0.2refusedupdated Mar 2026Dec 2025refused Feb 2026Mar 2026Wiltshire4.5
Larkhill Garrison Glover Roadsolar farmsolar farm—approved, not builtupdated Aug 2024Mar 2023granted Jul 2024Aug 2024Wiltshire4.9
Land at Court Farmbattery storagebattery storage—refused on appealupdated Sep 2019Jan 2018—Sep 2019Wiltshire6.9

Distance from the average position of the SP4 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm6123089.9
Rooftop solar302010.3
Battery storage210010

MW in pipeline: pending, approved and under-construction capacity.

How Wiltshire decides solar, wind and battery applications

ApplicationsWiltshireUK
Decided applications (solar, wind, battery)14010,236
Refused18 (13%)19%
Solar refused13 of 11012%
Onshore wind refused1 of 145%
Battery storage refused4 of 2916%
Median time from submission to decision20.9 weeks17.0 weeks
Appeals lodged / allowed5 / 7—

All projects in Wiltshire

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near SP4, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.