Parkhouse Corner (Orta Solar) (6.6 MW)

Parkhouse Corner (Orta Solar) is a 6.6 MW solar farm project in Test Valley, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 23 February 2013; the record was last updated on 15 April 2013.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

6.6 MWsolar farm
operationalstatus in REPD
15 April 2013record last updated
Test Valleycouncil area

Planning timeline

DateStage
9 August 2012Application submitted
14 November 2012Planning permission granted
3 December 2012Construction started
23 February 2013Operational

Project details

Technology
solar farm
Capacity
6.6 MW
Status (REPD)
operational
Record last updated
15 April 2013
Operator or applicant
Orta Solar
Planning authority
Test Valley
Planning application reference
12/01725/FULLN
Site area
12.0 ha
Address (REPD)
Snoddington Farm, Salisbury Road, Shipton Bellinger, Tidworth
Council area (by location)
Test Valley
Time to decision
14 weeks
REPD reference
1385

Who decides

ApplicationsTest ValleyUK
Decided applications (solar, wind, battery)4910,236
Refused8 (16%)19%
Solar refused7 of 4112%
Onshore wind refused0 of 145%
Battery storage refused1 of 716%
Median time from submission to decision23.6 weeks17.0 weeks
Appeals lodged / allowed4 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Shipton Bellinger - Park House Corner Solar Farmsolar farm5.4operational0.6
Down Barn Farmsolar farm49.9approved, not built0.8
Manor Farm (Thruxton)solar farm12.5application withdrawn3.3
Lains Farmsolar farm5operational4.4
Cholderton Road, Quarley Solar Farmsolar farm22.5approved, not built4.6
Perham Down - Meadow Solar Farm & Battery Storagesolar farm49.9approved, not built5.1
Boscombe Airfieldsolar farm12.3operational6.6
South Park Solar Farmsolar farm15approved, not built7.6
Blackthorn Solar Farmsolar farm40application submitted7.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.1955, -1.6752).