Lains Farm (5 MW solar farm)

Lains Farm is a 5 MW solar farm project in Test Valley, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 24 March 2016; the record was last updated on 1 July 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
1 July 2016record last updated
Test Valleycouncil area

Planning timeline

DateStage
5 December 2014Application submitted
17 July 2015Planning permission granted
24 March 2016Operational
1 May 2016Construction started

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
1 July 2016
Operator or applicant
INRG
Planning authority
Test Valley
Planning application reference
14/03017/FULLN
Site area
11.0 ha
Address (REPD)
Land at Lains Farm, Lains Paddock, Quarley, Andover, Hampshire
Council area (by location)
Test Valley
Time to decision
32 weeks
REPD reference
1840

Who decides

ApplicationsTest ValleyUK
Decided applications (solar, wind, battery)4910,236
Refused8 (16%)19%
Solar refused7 of 4112%
Onshore wind refused0 of 145%
Battery storage refused1 of 716%
Median time from submission to decision23.6 weeks17.0 weeks
Appeals lodged / allowed4 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Cholderton Road, Quarley Solar Farmsolar farm22.5approved, not built0.2
Manor Farm (Thruxton)solar farm12.5application withdrawn1.8
Perham Down - Meadow Solar Farm & Battery Storagesolar farm49.9approved, not built3.0
Shipton Bellinger - Park House Corner Solar Farmsolar farm5.4operational3.8
Parkhouse Corner (Orta Solar)solar farm6.6operational4.4
South Park Solar Farmsolar farm15approved, not built5.1
Down Barn Farmsolar farm49.9approved, not built5.2
Andover Solar Farmsolar farm5operational5.4
Saxley Farmsolar farm5operational6.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.1987, -1.6116).