Andover Solar Farm (5 MW)

Andover Solar Farm is a 5 MW solar farm project in Test Valley, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 22 March 2013; the record was last updated on 18 November 2013.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
18 November 2013record last updated
Test Valleycouncil area

Planning timeline

DateStage
1 March 2011Application submitted
29 September 2011Planning permission granted
22 March 2013Operational

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
18 November 2013
Operator or applicant
The Clark Trustees
Planning authority
Test Valley
Planning application reference
11/00529/FULLN
Site area
15.8 ha
Address (REPD)
Andover Business Park, Monxton Road, Andover, Hampshire
Council area (by location)
Test Valley
Time to decision
30 weeks
REPD reference
1570

Who decides

ApplicationsTest ValleyUK
Decided applications (solar, wind, battery)4910,236
Refused8 (16%)19%
Solar refused7 of 4112%
Onshore wind refused0 of 145%
Battery storage refused1 of 716%
Median time from submission to decision23.6 weeks17.0 weeks
Appeals lodged / allowed4 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Hatherden Farmsolar farm49.9operational4.5
Cholderton Road, Quarley Solar Farmsolar farm22.5approved, not built5.3
Lains Farmsolar farm5operational5.4
Abbots Annsolar farm7operational5.5
Cowdown Lanesolar farm40operational5.6
Saxley Farmsolar farm5operational5.6
South Park Solar Farmsolar farm15approved, not built5.6
Westover Farmsolar farm7operational5.8
South Way, Walworth Business Park Solar Photovoltaicsrooftop solar5.2application withdrawn5.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.2112, -1.5364).