Abbots Ann (7 MW solar farm)

Abbots Ann is a 7 MW solar farm project in Test Valley, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 30 March 2015; the record was last updated on 13 May 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

7 MWsolar farm
operationalstatus in REPD
13 May 2015record last updated
Test Valleycouncil area

Planning timeline

DateStage
4 September 2014Application submitted
23 January 2015Planning permission granted
1 February 2015Construction started
30 March 2015Operational

Project details

Technology
solar farm
Capacity
7 MW
Status (REPD)
operational
Record last updated
13 May 2015
Operator or applicant
British Solar Renewables
Planning authority
Test Valley
Planning application reference
14/02110/FULLN
Address (REPD)
Dipden Bottom Lane, Goodworth, Clatford, Hampshire
Council area (by location)
Test Valley
Time to decision
20 weeks
REPD reference
4874

Who decides

ApplicationsTest ValleyUK
Decided applications (solar, wind, battery)4910,236
Refused8 (16%)19%
Solar refused7 of 4112%
Onshore wind refused0 of 145%
Battery storage refused1 of 716%
Median time from submission to decision23.6 weeks17.0 weeks
Appeals lodged / allowed4 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Westover Farmsolar farm7operational0.5
Saxley Farmsolar farm5operational1.7
Winchester Road, Wherwell Solar Farmsolar farm45.9approved, not built3.7
Cowdown Lanesolar farm40operational5.1
Andover Solar Farmsolar farm5operational5.5
Solar Farm at Gander Down Solar Farmsolar farm6.2approved, not built6.1
Eveley Farmsolar farm49operational6.4
Somborne Park Roadsolar farm5refused6.6
South Way, Walworth Business Park Solar Photovoltaicsrooftop solar5.2application withdrawn7.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.1636, -1.5123).