Energy Projects Near You

Cowdown Lane (40 MW solar farm)

Cowdown Lane is a 40 MW solar farm project in Test Valley, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 23 March 2016; the record was last updated on 2 February 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

40 MWsolar farm
operationalstatus in REPD
2 February 2017record last updated
Test Valleycouncil area

Planning timeline

DateStage
1 May 2014Application submitted
15 October 2014Refused by the planning authority
22 June 2015Appeal lodged
24 December 2015Planning permission granted
24 December 2015Appeal allowed
1 January 2016Construction started
23 March 2016Operational

Project details

Technology
solar farm
Capacity
40 MW
Status (REPD)
operational
Record last updated
2 February 2017
Operator or applicant
Equitix
Planning authority
Test Valley
Planning application reference
14/00949/FULLN
Appeal reference
APP/C1760/W/15/3016531
Address (REPD)
Land West Of Cowdown Lane, Goodworth Clatford, Andover
Council area (by location)
Test Valley
Time to decision
86 weeks
REPD reference
1983

Who decides

ApplicationsTest ValleyUK
Decided applications (solar, wind, battery)4910,236
Refused8 (16%)19%
Solar refused7 of 4112%
Onshore wind refused0 of 145%
Battery storage refused1 of 716%
Median time from submission to decision23.6 weeks17.0 weeks
Appeals lodged / allowed4 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Winchester Road, Wherwell Solar Farmsolar farm45.9approved, not built2.2
South Way, Walworth Business Park Solar Photovoltaicsrooftop solar5.2application withdrawn2.2
Westover Farmsolar farm7operational5.0
Abbots Annsolar farm7operational5.1
Lower Wyke Farm, St Mary Bourne Solar Farmsolar farm21approved, not built5.4
Andover Solar Farmsolar farm5operational5.6
Owls Lodge Farmsolar farm5operational6.2
Owls Lodge Farm Extensionsolar farm5operational6.5
Saxley Farmsolar farm5operational6.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.1961, -1.4601).