Energy Projects Near You

Solar, wind and battery projects near Whitchurch (RG28)

13 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of RG28 (Basingstoke and Deane): 4 approved but not yet running, 4 operational. The largest live scheme is Lower Wyke Farm, St Mary Bourne Solar Farm (21 MW solar farm, approved on 11 June 2026, not yet built), 5.5 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

13projects within 10 km
0awaiting a decision
4approved, not running
4operational

Projects within 10 km of RG28

Projects of 1 MW and more (9)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Overtonsolar farmsolar farm4operationalupdated Mar 2016Jun 2014granted Dec 2014Mar 2016Basingstoke and Deane4.7
Bullington Cross Wind Farm (7 of 14 turbines Winchester City Council)wind farmwind farm14appeal withdrawnupdated Jul 2015Apr 2013refused Jun 2014Jul 2015Winchester5.4
Bullington Cross Wind Farm (Basingstoke and Deane)wind farmwind farm8appeal withdrawnupdated Jul 2015Apr 2013refused Jun 2014Jul 2015Winchester5.4
Bullington Cross Wind Farm (3 of 14 turbines Test Valley BC)wind farmwind farm6appeal withdrawnupdated Jul 2015Apr 2013refused Jun 2014Jul 2015Winchester5.4
Lower Wyke Farm, St Mary Bourne Solar Farmsolar farmsolar farm21approved, not builtupdated Jul 2026Aug 2023granted Jun 2026Jul 2026Basingstoke and Deane5.5
Owls Lodge Farm Extensionsolar farmsolar farm5operationalupdated Mar 2014Jul 2012granted Sep 2012Mar 2014Test Valley5.6
Owls Lodge Farmsolar farmsolar farm5operationalupdated Feb 2014Feb 2011granted Oct 2011Feb 2014Test Valley6.1
South Way, Walworth Business Park Solar Photovoltaicsrooftop solarrooftop solar5.2application withdrawnupdated May 2025Feb 2025—May 2025Test Valley8.3
Cowdown Lanesolar farmsolar farm40operationalupdated Feb 2017May 2014granted Dec 2015Feb 2017Test Valley9.6
Smaller schemes under 1 MW, mostly rooftop solar (4)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Southley Farm Buildings, Overtonrooftop solarrooftop solar0.3approved, not builtupdated Mar 2023Jan 2023granted Mar 2023Mar 2023Basingstoke and Deane5.8
Ocado Distribution Centre, South Wayrooftop solarrooftop solar—refusedupdated Sep 2025Jul 2025refused Sep 2025Sep 2025Test Valley8.3
R Twining And Company, South Wayrooftop solarrooftop solar1approved, not builtupdated Aug 2023Jul 2023granted Aug 2023Aug 2023Test Valley8.3
Walworth Business Park Solar Photovoltaics panelrooftop solarrooftop solar0.2approved, not builtupdated Jun 2022Jun 2022granted Jul 2022Jun 2022Test Valley8.3

Distance from the average position of the RG28 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm5014021
Rooftop solar503011.5
Wind farm300000

MW in pipeline: pending, approved and under-construction capacity.

How Basingstoke and Deane decides solar, wind and battery applications

ApplicationsBasingstoke and DeaneUK
Decided applications (solar, wind, battery)3010,236
Refused8 (27%)19%
Solar refused5 of 2212%
Onshore wind refused1 of 145%
Battery storage refused2 of 716%
Median time from submission to decision26.3 weeks17.0 weeks
Appeals lodged / allowed4 / 5—

All projects in Basingstoke and Deane

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.