Bullington Cross Wind Farm (Basingstoke and Deane) (8 MW)
Bullington Cross Wind Farm (Basingstoke and Deane) is an 8 MW wind farm project in Winchester, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: appeal withdrawn; the record was last updated on 17 July 2015.
8 MWwind farm
appeal withdrawnstatus in REPD
17 July 2015record last updated
Winchestercouncil area
Planning timeline
| Date | Stage |
|---|---|
| 8 April 2013 | Application submitted |
| 17 June 2014 | Refused by the planning authority |
| 26 January 2015 | Appeal lodged |
| 13 July 2015 | Appeal withdrawn |
Project details
- Technology
- wind farm
- Capacity
- 8 MW
- Status (REPD)
- appeal withdrawn
- Record last updated
- 17 July 2015
- Operator or applicant
- EDF
- Planning authority
- Winchester
- Planning application reference
- 13/00046/FUL
- Appeal reference
- APP/H1705/W/14/3001603
- Turbines
- 4
- Address (REPD)
- Land At Bullington Cross, Upper Norton Farm, Sutton Scotney, Hants
- Council area (by location)
- Winchester
- Time to decision
- 62 weeks
- REPD reference
- 4096
Who decides
| Applications | Winchester | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 37 | 10,236 |
| Refused | 4 (11%) | 19% |
| Solar refused | 0 of 24 | 12% |
| Onshore wind refused | 3 of 3 | 45% |
| Battery storage refused | 1 of 10 | 16% |
| Median time from submission to decision | 14.7 weeks | 17.0 weeks |
| Appeals lodged / allowed | 3 / 0 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Bullington Cross Wind Farm (7 of 14 turbines Winchester City Council) | wind farm | 14 | appeal withdrawn | <0.1 |
| Bullington Cross Wind Farm (3 of 14 turbines Test Valley BC) | wind farm | 6 | appeal withdrawn | <0.1 |
| Owls Lodge Farm Extension | solar farm | 5 | operational | 3.9 |
| Owls Lodge Farm | solar farm | 5 | operational | 4.3 |
| Three Maids Hill Solar Farm | solar farm | 25 | operational | 8.7 |
| Lower Wyke Farm, St Mary Bourne Solar Farm | solar farm | 21 | approved, not built | 9.0 |
| Woodmancott Down | wind farm | 18 | refused | 9.1 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.1887, -1.3118).