Owls Lodge Farm Extension (5 MW solar farm)

Owls Lodge Farm Extension is a 5 MW solar farm project in Test Valley, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 31 December 2013; the record was last updated on 24 March 2014.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
24 March 2014record last updated
Test Valleycouncil area

Planning timeline

DateStage
9 July 2012Application submitted
5 September 2012Planning permission granted
31 December 2013Operational

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
24 March 2014
Operator or applicant
Anesco
Planning authority
Test Valley
Planning application reference
12/01186/FULLN
Site area
4.4 ha
Address (REPD)
Nuns Walk Longparish Hampshire
Council area (by location)
Test Valley
Time to decision
8 weeks
REPD reference
1538

Who decides

ApplicationsTest ValleyUK
Decided applications (solar, wind, battery)4910,236
Refused8 (16%)19%
Solar refused7 of 4112%
Onshore wind refused0 of 145%
Battery storage refused1 of 716%
Median time from submission to decision23.6 weeks17.0 weeks
Appeals lodged / allowed4 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Owls Lodge Farmsolar farm5operational0.6
Bullington Cross Wind Farm (Basingstoke and Deane)wind farm8appeal withdrawn3.9
Bullington Cross Wind Farm (7 of 14 turbines Winchester City Council)wind farm14appeal withdrawn3.9
Bullington Cross Wind Farm (3 of 14 turbines Test Valley BC)wind farm6appeal withdrawn3.9
Lower Wyke Farm, St Mary Bourne Solar Farmsolar farm21approved, not built6.4
Cowdown Lanesolar farm40operational6.5
South Way, Walworth Business Park Solar Photovoltaicsrooftop solar5.2application withdrawn6.6
Winchester Road, Wherwell Solar Farmsolar farm45.9approved, not built6.9
Three Maids Hill Solar Farmsolar farm25operational8.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.1876, -1.3674).